Status
Tender opening completed
Bidding package name
Procurement of materials and equipment
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project: Repairing culverts at Tram Pump canal (6 Co Lep) adjacent to Binh Hoa canal
Contract execution period
45 day
Contractor selection methods
Competitive Offer
Award date
09:00 27/11/2024
Bid opening completion time
09:22 27/11/2024
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)