Status
Complete opening of financial documents
Bidding package name
Safety inspection of dams and reservoirs at Hua Na hydroelectric project (cycle 2)
Investor
HUA NA HYDROPOWER JOINT STOCK COMPANY
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Safety inspection of dams and reservoirs at Hua Na hydroelectric project (cycle 2)
Contract execution period
60 day
Contractor selection methods
Competitive Bidding
Award date
10:00 13/07/2024
Bid opening completion time
10:00 13/07/2024
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)
Price Tender value
1.833.847.832 VND