Contractor Selection Plan Name
Repairing damage to the foundation and road surface of sections: Km55+150 - Km55+865, Km56+643 - Km57+103, Km57+318 - Km57+481, Km58+150 - Km58+733, Km64+100 - Km64+350 , Km67+000 - Km67+422, Km67+900 - Km68+317, Km68+700 - Km69+077, Km72+253 - Km72+837, Km74+000 - Km74+500; Repairing the drainage system in sections: Km61+600 - Km62+300, Km62+900 - Km63+220, Km69+200 - Km69+600, Km70+000 - Km70+350, Km73+500 - Km73+700, Km74 +200 - Km74+700, Km74+850 - Km75+500; Repair expansion joints of 05 bridges; Repair and reinforce the shoulders of sections: Km54+350 - Km54+600, Km67+800 - Km68+100, Km72+450 - Km72+650, Km72+800 - Km73+100, Km73+500 - Km73+700 and repair traffic safety system from Km54+350 - Km75+500, National Highway 55, Binh Thuan province