Status
Tender opening completed
Bidding package name
Tender package No 04: Construction work
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Project: Repairing underground spillway Pec Na II, Bac Son commune
Contract execution period
180 day
Contractor selection methods
Competitive Bidding
Award date
08:00 14/07/2023
Bid opening completion time
08:48 14/07/2023
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
2.182.932.000 VND