Investment objective
Ensure the continuous operation of the production line when the grid is out of power. Improve the capacity to active in production, improve working conditions for workers. Avoid depending entirely on the national electricity grid; Avoid damage to the device due to sudden power failure
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500047421-00
Name of project
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Authority that issues the decision
Tổng giám đốc Công ty
Approval date
05/09/2025
Approval ID
353/QĐ-PLVĐ
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 1
1.3 -phase generator shopping
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Perform 01 3 -phase generator with the following specifications: 1. - Engine power at rated speed: ≤ 414 kW; ≤ 555HP - Suction and cooling: charging and air -cooled tubo - Number of cylinders and layout types: 8 cylinders of V -type - Engine speed: ≤ 1,500 v/min - Speeder: Electronic control - Fuel consumption at full load: ≤ 89.3 liters/hour - Fuel tank capacity: ≥ 700 liters - Cooling water capacity: ≥ 80 liters 2. Machine (head) power generator - Design: No brushless, a bearing, magnetic field - Stator: Step 2/3 - Rotor: A bearing, floppy disk - Continuous power: ≤ 400/320 (KVA/KW) - Backup capacity: ≤ 440/352 (KVA/KW) - Voltage: (400/230) volt - Frequency: 50 Hz - Insulation: Grade H - Protection level: ≥ ip21 - Type of self -stimulus: Yes - Automatic voltage regulator: Yes - Standard increasing temperature: 125 - 163 0C (continuous operation) 3. Control module: a. Characteristic: - Monitor the power source and start/off the transmitter; - Automatic control of transmitter and grid contact; - Monitoring engine performance and generator capacity; - Alarm by LED. b. Show via LCD screen: -Generator voltage (L-L/L-N); - Engine oil pressure (PSI/Bar; - generator current (L1, L2, L3); - Motor temperature (OC & Of); - Generator frequency (Hz); - % of rated capacity; - Power coefficient cosφ; - Battery voltage; - Total running time; -Grid voltage (phase) KVA, KWh. c. Warning: - The speed is too high/low; - High/low battery; - Incarnation/stop; - Excessive charging error; - High/low generator voltage; - Low oil pressure; - Emergency stop; - High temperature; - Overload KW; - Unbalanced download; - Error of independent ground touch. d. Directive LED light: - There is electricity; - There are generators; - Load is using electricity; - Load is using generator. 4. Cold steel-made steel shell 2-5mm, powder coating, standard soundproofing materials.
Capital source details
Own capital of the company
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "3 -phase generator". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "3 -phase generator" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 5

You did not use the site, Click here to remain logged. Timeout: 60 second