Bidder Selection Plan

Additional Tra Tan and sewer 26/3

  Watching      
Find: 12:48 12/09/2025
Contractor Selection Plan ID
PL2500215324-00
Publishing time
09:56 12/09/2025
Posting Status
Published
Contractor selection plan name
Additional Tra Tan and sewer 26/3
Investment objective
Control fresh water to stabilize agricultural production in planting areas Fruit trees have high economic value, actively convert agricultural production models adapt to climate change and meet market demand; Ensure security and safety Grant water serving people and combining to strengthen rural traffic routes
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300031607-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
6 Years
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng công trình Nông nghiệp và phát triển nông thôn tỉnh Đồng Tháp
Approval date
10/09/2025
Approval ID
28/QĐ-BQLDANN
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 8
1.Construction of Tra Tan tribute and sewer 26/3
Tender/ Prequalification Notice ID
Contract execution period
420 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of open culverts (Cung Tra Tan) and boxes (sewers March 26) with reinforced concrete, equipment installation and electrical relocation, ensuring water and road traffic safety
Capital source details
Central and local budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
2.Insurance of Tra Tan tribute project
Tender/ Prequalification Notice ID
Contract execution period
420 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Project risk insurance
Capital source details
Central and local budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Advice on making reports on environmental protection (Tra Tan and sewer 26/3)
Tender/ Prequalification Notice ID
Contract execution period
420 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Making a report on environmental protection (Tra Tan and sewer 26/3)
Capital source details
Central and local budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Consulting on construction norms for construction (Tra Tan and sewer 26/3)
Tender/ Prequalification Notice ID
Contract execution period
420 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Check and review the application norms and characteristics of the project
Capital source details
Central and local budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Consulting supervision of installation of Tra Tan cylinder equipment
Tender/ Prequalification Notice ID
Contract execution period
420 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of equipment installation equipment for Tra An cylinder
Capital source details
Central and local budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Consulting on construction drawing drawings and estimates of relocation of electrical systems for site clearance (Tra Tan sluice and sewer 26/3)
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Design of construction drawings and electricity relocation estimates
Capital source details
Central and local budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
7.Consulting on examining construction drawings and estimates of relocation of electrical systems for site clearance (Tra Tan and sewer 26/3)
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Examination of construction drawing designs and electricity relocation estimates
Capital source details
Central and local budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
8.Consulting on supervision and installation of low -voltage, medium voltage electrical equipment and transformer stations (Tra Tan and sewer 26/3)
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction and installation of voltage, medium voltage and transformer stations
Capital source details
Central and local budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Additional Tra Tan and sewer 26/3". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Additional Tra Tan and sewer 26/3" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 5

You did not use the site, Click here to remain logged. Timeout: 60 second