Bidder Selection Plan

Adjusting and supplementing the contractor selection plan for Tung Thien High School Construction project

  Watching      
Find: 08:40 19/11/2025
Contractor Selection Plan ID
PL2500177729-01
Publishing time
08:38 19/11/2025
Posting Status
Published
Contractor selection plan name
Adjusting and supplementing the contractor selection plan for Tung Thien High School Construction project
Investment objective
Investing in building new Tung Thien High School to meet the learning and teaching needs of the school, contributing to improving the quality of education and striving to meet the national standard level 2
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500042801-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
Ban QLDA đầu tư - hạ tầng phường Tùng Thiện
Approval date
15/11/2025
Approval ID
124/QĐ-BQLDA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Filter name, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 17
1.Plug mold, measure map for land clearance
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Make a plan to plug landmarks, landmarks and hand over the boundary boundary in addition to the land use owner, measure the land parcel of land withdrawn, edit the map of the land clearance ...
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
July, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.E-HSMT, E-HSDT Bidding Package Designing BVTC Design records
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
E-HSMT, E-HSDT evaluation, Bidd's selection results report
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
July, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.E-HSMT appraisal, the results of the contractor selection package for the design of BVTC Design
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Comments, E-HSMT evaluation, contractor selection results for the basis for approval
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
July, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Make construction drawing design records
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Making explanations, estimates, construction drawings ...
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
July, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Verification of BVTC design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Comment, evaluate the contents of BVTC design and cost estimates according to current regulations
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Prepare E-Bidding, evaluate E-Bidding for construction bidding packages, construction supervision, equipment procurement and installation
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
E-HSMT, E-HSDT evaluation, Bidd's selection results report
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
7.Appraisal of E-HSMT, contractor selection results for construction bidding packages, construction supervision, equipment procurement and installation
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Comments, E-HSMT evaluation, contractor selection results for the basis for approval
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
8.Construction of technical infrastructure + support
Tender/ Prequalification Notice ID
Contract execution period
600 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of technical infrastructure + support
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
9.Supervision of construction of technical and auxiliary infrastructure
Tender/ Prequalification Notice ID
Contract execution period
600 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Monitoring the quality, volume, progress, labor safety and environmental protection during the construction process
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
10.Insurance for construction of technical infrastructure + support
Tender/ Prequalification Notice ID
Contract execution period
600 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Determine the risk of compensation when the work occurs material loss during the process of construction and compensation for material damage and the 3rd person
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
11.Experimental static compression
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Processing the process, outline, static compression experiments, load -bearing testing of piles, reporting of static compression test results
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
12.Equipment cost appraisal
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Collect information on price and legal equipment for appraisal, reporting and pricing certificates
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
13.Construction of the main building block, fire protection, transformer station + equipment procurement and installation
Tender/ Prequalification Notice ID
Contract execution period
600 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Uncategoried
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of the main building block, fire protection, transformer station + equipment procurement and installation
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
14.Supervision of construction of the main building block, fire protection, transformer station + equipment procurement and installation
Tender/ Prequalification Notice ID
Contract execution period
600 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction of the main building block, fire protection, transformer station + equipment procurement and installation
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
15.Construction insurance for the main building block, fire protection, transformer station
Tender/ Prequalification Notice ID
Contract execution period
600 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Determine the risk of compensation when the project occurs during construction...
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
16.Make environmental registration records
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare project environmental registration documents according to current legal regulations
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
17.Audit
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Adjusting and supplementing the contractor selection plan for Tung Thien High School Construction project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Adjusting and supplementing the contractor selection plan for Tung Thien High School Construction project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 9

You did not use the site, Click here to remain logged. Timeout: 60 second