Approval of contractor selection plan for component project 5: Repairing and upgrading Cua Nghe reservoir, Bo Trach district under the project of repairing and upgrading key reservoirs and dams in Quang Binh province.
Approval of contractor selection plan for component project 5: Repairing and upgrading Cua Nghe reservoir, Bo Trach district under the project of repairing and upgrading key reservoirs and dams in Quang Binh province.
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
QD so 266 cua UBND tinh 26-1-2022.pdf
List of Bid:
Number of packages: 4
1.Consulting to make outline of tasks and survey estimates, design construction drawings and cost estimates
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
According to fixed unit price
Prequalification
No
Location
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approval of contractor selection plan for component project 5: Repairing and upgrading Cua Nghe reservoir, Bo Trach district under the project of repairing and upgrading key reservoirs and dams in Quang Binh province.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approval of contractor selection plan for component project 5: Repairing and upgrading Cua Nghe reservoir, Bo Trach district under the project of repairing and upgrading key reservoirs and dams in Quang Binh province." plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.