Bidder Selection Plan

Approval of the contractor selection plan (2nd time) of the project: Investment in construction of technical infrastructure of the resettlement area and site clearance of the central area of ​​Pham Ngu Lao ward, Hai Duong city - Area 1

  Watching      
Find: 14:18 26/06/2023
Contractor Selection Plan ID
PL2300103299-00
Publishing time
14:15 26/06/2023
Posting Status
Published
Contractor selection plan name
Approval of the contractor selection plan (2nd time) of the project: Investment in construction of technical infrastructure of the resettlement area and site clearance of the central area of ​​Pham Ngu Lao ward, Hai Duong city - Area 1
Investment objective
Site clearance for Hai Duong Porcelain Factory, Hoa Su Kindergarten, Book Publication Joint Stock Company, households and construction of resettlement areas, preschool and central urban area project implementation Pham Ngu Lao ward, Hai Duong city (area 1) according to the approved planning.
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300014995-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Location
Authority that issues the decision
UBND thành phố Hải Dương, tỉnh Hải Dương
Approval date
23/06/2023
Approval ID
Số 2124/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 9
1.Prepare bidding documents, evaluate bids for construction bidding packages (phase 1 of the project) and install equipment (living electricity); Posting contractor selection information.
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương
2.Supervision of construction (phase 1 of the project) and equipment installation (living electricity).
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương
3.Construction (phase 1 of the project) and equipment installation (living electricity) and other expenses.
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
June, 2023
Type of contract
Fixed unit price
Prequalification
No
Location
Hải Dương City, Hải Dương
4.Appraisal of bidding documents, appraisal of construction project management package (phase 1 of the project) and equipment installation (living electricity).
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương
5.Prepare bidding documents, evaluate bid packages for construction supervision (phase 1 of the project) and equipment installation (living electricity); post LCNT information.
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương
6.Construction insurance (phase 1 of the project).
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương
7.Appraisal of bidding documents, appraisal of construction management and construction supervision bidding package (phase 1 of the project) and equipment installation (living electricity).
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương
8.Plug the lot divider.
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương
9.Static compression test and load test of concrete piles.
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget and capital from land development fund. The city budget shall be arranged when the balance conditions are met.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location
Hải Dương City, Hải Dương

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approval of the contractor selection plan (2nd time) of the project: Investment in construction of technical infrastructure of the resettlement area and site clearance of the central area of ​​Pham Ngu Lao ward, Hai Duong city - Area 1". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approval of the contractor selection plan (2nd time) of the project: Investment in construction of technical infrastructure of the resettlement area and site clearance of the central area of ​​Pham Ngu Lao ward, Hai Duong city - Area 1" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 11

You did not use the site, Click here to remain logged. Timeout: 60 second