Bidder Selection Plan

Approval of the Procurement Plan for the Disaster Relief and River Dak Snghe Landslide Mitigation Project (Dak Bla), Kon Braih Commune.

  Watching  
Project Contractor selection plan Bid award
Find: 09:40 27/08/2026
Contractor Selection Plan ID
PL2600279479-00
Publishing time
09:40 27/08/2026
Posting Status
Published
Contractor selection plan name
Approval of the Procurement Plan for the Disaster Relief and River Dak Snghe Landslide Mitigation Project (Dak Bla), Kon Braih Commune.
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Spending Category
Investment and Development Spending
Authority that issues the decision
Ban Quản lý dự án đầu tư Tây Quảng Ngãi
Approval date
26/08/2026
Approval ID
176/QĐ-BQLDA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 14
1.Procurement Package No. 01-TV: Development of Survey Tasks, Technical Specifications, and Cost Estimates
Tender/ Prequalification Notice ID
Contract execution period
5 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Develop tasks for terrain and geological surveys; - Prepare technical specifications and cost estimates.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
2.Procurement Tender package No 02-TV: Survey, preparation of dossiers for national and regional historical sites, and overall cost estimation.
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Conduct site surveys and geological assessments; - Prepare the project's cultural heritage assessment report; - Prepare the financial viability report and overall budget.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
3.Contract No. 03-TV: Supervision of terrain and geological survey work
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Conduct site surveys and geological investigations.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
4.Procurement Tender package No 04-TV: Inspection of the National Center for Science and Technology
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out verification of F/S Documents.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
5.Contract No. 05-TV: Construction Supervision
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction supervision.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
6.Procurement Tender package No 06-TV: Independent Audit
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Conduct an independent audit of the project.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter IV, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
7.Bid No. 07-TV: Consulting services for GPS monument installation
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Plug the landmark for land clearance
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
8.Procurement Tender package No 08-TV: Consulting services for land clearance and compensation work.
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Measurements for public service purposes
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
9.Procurement Package 09-TV: Survey, development of a demolition plan, and cost estimation for explosive ordnance disposal.
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Conducting investigative surveys, developing a demolition plan, and estimating the cost of mine clearance and explosives removal.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
10.Contract No. 10-TV: Supervision of demolition and clearance of explosive ordnance
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carrying out the supervision of construction and construction of mines and mines and explosives
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
11.Contract No. 11-TV: Inspection of the State Bank of Vietnam and overall cost estimation
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out the review of the financial statements and prepare the overall budget.
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
12.Bidding package No. 01-XL: Construction construction
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and installation work + resource taxes + contingency for unforeseen construction work (5%)
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
Fixed unit price
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
13.Contract No. 01-PTV: Demining and Explosives Handling
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of clearing mines and explosives
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No
14.Tender No. 02-PTV: Construction site insurance during construction.
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance during construction
Capital source details
The central government budget is used to address the consequences and prevent/mitigate natural disasters within the province (as allocated in Decision No. 441/QD-UBND dated June 26, 2026 of the Provincial People's Committee).
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
By percentage
Implementation location
Xã Kon Braih, Province Quảng Ngãi
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approval of the Procurement Plan for the Disaster Relief and River Dak Snghe Landslide Mitigation Project (Dak Bla), Kon Braih Commune.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approval of the Procurement Plan for the Disaster Relief and River Dak Snghe Landslide Mitigation Project (Dak Bla), Kon Braih Commune." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second