Bidder Selection Plan

Approval of the second phase of contractor selection plan

  Watching    
Project Contractor selection plan Tender notice Bid award
Find: 09:57 27/02/2019
Contractor selection plan ID
20190231637-00
Publication date
09:57 27/02/2019
Publication status
Actual notification
Contractor selection plan name
Approval of the second phase of contractor selection plan
Investor
Ban Quản lý Đầu tư và Xây dựng Thủy lợi 1 làm chủ đầu tư hợp phần xây dựng công trình đầu mối hồ chứa; UBND huyện Lạc Sơn làm chủ đầu tư hợp phần bồi thường, hỗ trợ và tái định cư; UBND tỉnh Hòa Bình quyết định chủ đầu tư hợp phần xây dựng đường ống dẫn nước.
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20180504618-03
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
25/02/2019
Approval ID
Số 632/QĐ-BNN-XD
List of Bid:
Number of packages: 6
1.Tender package No 16- Consultant and supervision of demining, demining, explosives
Tender/ Prequalification Notice ID
Contract Period
03 months
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Government Bonds
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2019
Contract Type
All in one
Prequalification
No
Location
2.Tender package No 17 -Construction and equipment installation of key clusters
Tender/ Prequalification Notice ID
Contract Period
28 months
Domestic/ International
International
Bidding method
Directly
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Government Bonds
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2019
Contract Type
According to the adjusted unit price
Prequalification
No
Location
3.Tender package No 18- Supervision of construction and equipment installation
Tender/ Prequalification Notice ID
Contract Period
28 months
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Government Bonds
Contractor Selection Type
Self-implementation, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2019
Contract Type
All in one
Prequalification
No
Location
4.Tender package No 19- Construction insurance
Tender/ Prequalification Notice ID
Contract Period
28 months
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Government Bonds
Contractor Selection Type
Competitive offers, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
Location
5.Tender package No 20-Environmental monitoring and supervision consultancy
Tender/ Prequalification Notice ID
Contract Period
28 months
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Government Bonds
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
Location
6.Package 21 -Consultancy on geological description of foundation pits during construction
Tender/ Prequalification Notice ID
Contract Period
15 months
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Government Bonds
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approval of the second phase of contractor selection plan". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approval of the second phase of contractor selection plan" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 147

You did not use the site, Click here to remain logged. Timeout: 60 second