Bidder Selection Plan

Approve the contractor selection plan for the project: Renovating and upgrading project items that have been invested in the construction of Bung Lao High School

  Watching      
Find: 18:31 19/12/2025
Contractor Selection Plan ID
PL2500355388-00
Publishing time
18:18 19/12/2025
Posting Status
Published
Contractor selection plan name
Approve the contractor selection plan for the project: Renovating and upgrading project items that have been invested in the construction of Bung Lao High School
Investment objective
Ensure the conditions of facilities to serve teaching, learning and educational activities of officials, teachers and students, thereby improving the quality of education and training; At the same time, it ensures the aesthetics of schools and classrooms, avoids deterioration of buildings, improves safety, and prolongs the life of constructed construction items.
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500070893-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
Sở Giáo dục và Đào tạo tỉnh Điện Biên
Approval date
18/12/2025
Approval ID
1953/QĐ-SGDĐT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Project management consultancy
Tender/ Prequalification Notice ID
Contract execution period
13 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction project management
Capital source details
Education capital in the annual budget revenue and expenditure estimates, assigned in Decision No. 2259/QD-UBND dated December 12, 2024 of the Provincial People's Committee, on the assignment of local budget revenue and expenditure estimates in 2025 "school repair item 12,600 million VND" and education capital in 2026.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Consultancy on preparation and evaluation of tender documents
Tender/ Prequalification Notice ID
Contract execution period
50 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bid documents, evaluate bids for construction and installation bidding packages
Capital source details
Education capital in the annual budget revenue and expenditure estimates, assigned in Decision No. 2259/QD-UBND dated December 12, 2024 of the Provincial People's Committee, on the assignment of local budget revenue and expenditure estimates in 2025 "school repair item 12,600 million VND" and education capital in 2026.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
9 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision
Capital source details
Education capital in the annual budget revenue and expenditure estimates, assigned in Decision No. 2259/QD-UBND dated December 12, 2024 of the Provincial People's Committee, on the assignment of local budget revenue and expenditure estimates in 2025 "school repair item 12,600 million VND" and education capital in 2026.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Civil Works
Tender/ Prequalification Notice ID
Contract execution period
9 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Civil Works
Capital source details
Education capital in the annual budget revenue and expenditure estimates, assigned in Decision No. 2259/QD-UBND dated December 12, 2024 of the Provincial People's Committee, on the assignment of local budget revenue and expenditure estimates in 2025 "school repair item 12,600 million VND" and education capital in 2026.
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
21 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
Education capital in the annual budget revenue and expenditure estimates, assigned in Decision No. 2259/QD-UBND dated December 12, 2024 of the Provincial People's Committee, on the assignment of local budget revenue and expenditure estimates in 2025 "school repair item 12,600 million VND" and education capital in 2026.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approve the contractor selection plan for the project: Renovating and upgrading project items that have been invested in the construction of Bung Lao High School". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approve the contractor selection plan for the project: Renovating and upgrading project items that have been invested in the construction of Bung Lao High School" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second