Bidder Selection Plan

Approving the contractor selection plan for Cay Duong town resettlement project to serve the 500kV Long Phu - O Mon thermal power line

  Watching    
Project Contractor selection plan Tender notice Bid award
Find: 08:19 07/11/2018
Contractor selection plan ID
20181114376-00
Publication date
08:19 07/11/2018
Publication status
Actual notification
Contractor selection plan name
Approving the contractor selection plan for Cay Duong town resettlement project to serve the 500kV Long Phu - O Mon thermal power line
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20181113086-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
16/10/2018
Approval ID
1531/QĐ-UBND ngày 16 tháng 10 năm 2018
Related announcements

- Change: Notification form, Lowest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 11
1.Project management
Tender/ Prequalification Notice ID
Contract Period
780 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
Contract Type
All in one
Prequalification
No
Location
2.Design construction drawings - cost estimates
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
Contract Type
All in one
Prequalification
No
Location
3.Consultancy and design verification of BVTC
Tender/ Prequalification Notice ID
Contract Period
08 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
Contract Type
All in one
Prequalification
No
Location
4.Consultancy and verification of construction cost estimates
Tender/ Prequalification Notice ID
Contract Period
7 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
Contract Type
All in one
Prequalification
No
Location
5.Consulting on setting up bidding documents, analyzing and evaluating bids for construction and installation bidding packages
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2019
Contract Type
All in one
Prequalification
No
Location
6.Construction supervision consultant
Tender/ Prequalification Notice ID
Contract Period
150 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2019
Contract Type
All in one
Prequalification
No
Location
7.Construction insurance
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2019
Contract Type
All in one
Prequalification
No
Location
8.Construction audit
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
Contract Type
All in one
Prequalification
No
Location
9.Measurement, documentation for landmark planting, site clearance piles
Tender/ Prequalification Notice ID
Contract Period
15 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
Contract Type
All in one
Prequalification
No
Location
10.Construction and General Item Costs
Tender/ Prequalification Notice ID
Contract Period
150 days
Domestic/ International
International
Bidding method
Directly
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2019
Contract Type
All in one
Prequalification
No
Location
11.Check, clear mines
Tender/ Prequalification Notice ID
Contract Period
15 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Funds from the Southern Power Project Management Board (From the funding for compensation, support and resettlement for the 500kV Long Phu–O Mon Thermal Power Line)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approving the contractor selection plan for Cay Duong town resettlement project to serve the 500kV Long Phu - O Mon thermal power line". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approving the contractor selection plan for Cay Duong town resettlement project to serve the 500kV Long Phu - O Mon thermal power line" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 295

You did not use the site, Click here to remain logged. Timeout: 60 second