Bidder Selection Plan

Approving the design and construction of the multi-purpose gymnasium project in Hau Loc district

  Watching      
Find: 08:48 09/03/2022
Contractor selection plan ID
20210710254-01
Publication date
08:43 09/03/2022
Publication status
Actual notification
Contractor selection plan name
Approving the design and construction of the multi-purpose gymnasium project in Hau Loc district
Investor
UBND huyện Hậu Lộc
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210667851-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
04/07/2021
Approval ID
1287/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

Related announcements

- Change: Notification form, Bidding package number, total investment, Highest bid price, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 6
1.Bidding package No. 01 consulting on setting up bidding documents, evaluating bids of bidding packages
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
Contract Type
All in one
Prequalification
No
Location
2.Bidding package number 02 consulting design construction drawings
Tender/ Prequalification Notice ID
Contract Period
45 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
Contract Type
All in one
Prequalification
No
Location
3.Package 03 to verify construction drawing design and project
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
Contract Type
All in one
Prequalification
No
Location
4.Bidding package No. 5 consulting and supervision of construction works + equipment
Tender/ Prequalification Notice ID
Contract Period
12 months
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
Contract Type
All in one
Prequalification
No
Location
5.Tender package No 6 independent audit
Tender/ Prequalification Notice ID
Contract Period
2 months
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Contract Type
All in one
Prequalification
No
Location
6.Package 4 for construction work + equipment + insurance
Tender/ Prequalification Notice ID
Contract Period
12 months
Domestic/ International
International
Bidding method
Directly
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
Contract Type
According to fixed unit price
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approving the design and construction of the multi-purpose gymnasium project in Hau Loc district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approving the design and construction of the multi-purpose gymnasium project in Hau Loc district" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 75

You did not use the site, Click here to remain logged. Timeout: 60 second