Bidder Selection Plan

Approving the plan for selection of construction contractors: Trung Loc - Khanh Vinh Yen inter-commune road, Can Loc district

  Watching      
Find: 04:27 17/10/2021
Contractor selection plan ID
20210470412-00
Publication date
15:33 28/04/2021
Publication status
Actual notification
Contractor selection plan name
Approving the plan for selection of construction contractors: Trung Loc - Khanh Vinh Yen inter-commune road, Can Loc district
Investor
UBND huyện Can Lộc
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210470396-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
07/04/2021
Approval ID
1115/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

List of Bid:
Number of packages: 3
1.01.XL: Construction of an inter-commune road between Trung Loc - Khanh Vinh Yen
Tender/ Prequalification Notice ID
Contract Period
150 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Can Loc district budget and other lawful capital mobilization
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April 2021
Contract Type
All in one
Prequalification
No
Location
2.02.TVGS: Construction supervision consultant for package 01.XL
Tender/ Prequalification Notice ID
Contract Period
150 days
Domestic/ International
International
Bidding method
Directly
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Can Loc district budget and other lawful capital mobilization
Contractor Selection Type
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April 2021
Contract Type
All in one
Prequalification
No
Location
3.03.BH: Construction insurance
Tender/ Prequalification Notice ID
Contract Period
17 months
Domestic/ International
International
Bidding method
Directly
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Can Loc district budget and other lawful capital mobilization
Contractor Selection Type
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
April 2021
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approving the plan for selection of construction contractors: Trung Loc - Khanh Vinh Yen inter-commune road, Can Loc district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approving the plan for selection of construction contractors: Trung Loc - Khanh Vinh Yen inter-commune road, Can Loc district" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 17