Approving the plan to select the contractor for the second phase (remaining bidding packages) Project headquarters of the People's Procuracy of Tuyen Quang province
Approving the plan to select the contractor for the second phase (remaining bidding packages) Project headquarters of the People's Procuracy of Tuyen Quang province
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
QD phe duyet KHLCNT dot 2 Vien tinh 2020.pdf
List of Bid:
Number of packages: 12
1.Package 01: Construction and equipment (construction of items, anti-termites, air conditioning equipment, fire protection, outdoor electrical equipment, substation)
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
6.Tender package No 06: Consulting on setting up bidding documents, evaluating bids for supervision package of construction, installation and equipment installation
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
9.Package 09: Consultancy on appraisal of bidding documents, appraisal of contractor selection results for package of construction supervision and equipment installation
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
Contract Type
All in one
Prequalification
No
Location
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approving the plan to select the contractor for the second phase (remaining bidding packages) Project headquarters of the People's Procuracy of Tuyen Quang province". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approving the plan to select the contractor for the second phase (remaining bidding packages) Project headquarters of the People's Procuracy of Tuyen Quang province" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.