Bidder Selection Plan

Ba Lai 8 Bridge Construction Project on the coastal road of Ben Tre province

  Watching      
Find: 08:59 07/03/2024
Contractor Selection Plan ID
PL2400000100-01
Publishing time
08:56 07/03/2024
Posting Status
Published
Contractor selection plan name
Ba Lai 8 Bridge Construction Project on the coastal road of Ben Tre province
Investment objective
In order to promote the investment process of building coastal roads in Ben Tre province as well as creating a spillover effect, attracting investment in building and developing marine economic zones, industry, agriculture, and aquaculture high technology, tourism, and services for the coastal area of ​​Ben Tre province and the Mekong Delta region in a sustainable manner, in accordance with growth requirements and adaptation to climate change.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400000102-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Location
Authority that issues the decision
Ủy ban nhân dân tỉnh Bến Tre
Approval date
30/12/2023
Approval ID
3080/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Bidding package number, Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 27
1.Set up survey tasks, design construction and deploy after basic design
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
2.Survey, construction design, deploy after basic design
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
3.Verification of construction design and implementation after basic design
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
4.Verify construction estimates implemented after basic design
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
5.Investigate, survey and prepare construction plans and estimates for bomb, mine and explosive material clearance
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
6.Supervise construction of clearance and destruction of bombs, mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
7.Survey, design construction drawings and estimate return and relocation of the power grid
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
8.Survey, design construction drawings and estimate technical infrastructure relocation
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
9.Investigate and survey to establish alternative afforestation plans
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
10.Survey, technical design and estimate for replacement afforestation
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
11.Supervision of afforestation construction
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
12.Quality inspection and bridge load testing
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
13.Construction supervision of package No. 02 (section 2 Km9+534.68 - Km12+900)
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
14.Traffic safety inspection before putting the works into operation
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
15.Environmental monitoring and monitoring
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
16.Construction insurance for construction package No. 01 (section 1 Km0+00 - Km9+534.68)
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
17.Construction insurance for construction package No. 02 (section 2 Km9+534.68-Km12+900)
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Ba Tri District, Bến Tre
18.Construction insurance for construction package No. 03 (connecting line)
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
19.Insurance for construction and relocation of technical infrastructure
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
20.Insurance for construction, return, and relocation of the power grid
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
21.Construction of clearance, collection and destruction of bombs, mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
22.Construction and installation package No. 01 (section 1 Km0+00 - Km9+534.68)
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
According to adjusted unit price
Prequalification
No
Location
Bình Đại District, Bến Tre
23.Construction and installation package No. 02 (section 2 Km9+534.68 - Km12+900)
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
According to adjusted unit price
Prequalification
No
Location
Bình Đại District, Bến Tre
24.Construction and installation package No. 03 (connecting route)
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
According to adjusted unit price
Prequalification
No
Location
Bình Đại District, Bến Tre
25.Construction, return and relocation of the electrical system
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
26.Construction, return and relocation of technical infrastructure
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre
27.Construction of replacement forests and forest care and protection
Tender/ Prequalification Notice ID
Contract execution period
1550 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget to support regionally integrated projects in the medium-term investment plan for the period 2021 - 2025 is 1,499,800 million VND and the corresponding local budget in the medium-term investment plan for the period 2021 - 2025 is 755,200 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Bình Đại District, Bến Tre

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Ba Lai 8 Bridge Construction Project on the coastal road of Ben Tre province". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Ba Lai 8 Bridge Construction Project on the coastal road of Ben Tre province" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 212

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 7892 Projects are waiting for contractors
  • 528 Tender notices posted in the last 24 hours
  • 879 Contractor selection plan posted in the last 24 hours
  • 23863 Tender notices posted in the past month
  • 37720 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second