Bidder Selection Plan

Building Hoa Sua kindergarten, Yen Vien commune, Gia Lam district

  Watching      
Find: 20:56 16/10/2021
Contractor selection plan ID
20201267029-00
Publication date
16:24 21/12/2020
Publication status
Actual notification
Contractor selection plan name
Building Hoa Sua kindergarten, Yen Vien commune, Gia Lam district
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20201267016-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
01/02/2020
Approval ID
9269/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

List of Bid:
Number of packages: 6
1.Tender package No 1: Consultancy on design of construction drawings and estimates of main and auxiliary house items
Tender/ Prequalification Notice ID
Contract Period
150 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2020
Contract Type
All in one
Prequalification
No
Location
2.Bidding package 2: Consulting on making bidding documents, evaluating bids for package No. 1
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2020
Contract Type
All in one
Prequalification
No
Location
3.Tender package No 3: Consultancy on appraisal of bidding documents, results of contractor selection for package No. 1
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2020
Contract Type
All in one
Prequalification
No
Location
4.Package 4: Consulting on design of construction drawings and cost estimate of fire protection items
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
Contract Type
All in one
Prequalification
No
Location
5.Tender package No 5: Consulting on design of construction drawings and cost estimate of substation items
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
Contract Type
All in one
Prequalification
No
Location
6.Package 6: Consultancy and verification of construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Directly
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Building Hoa Sua kindergarten, Yen Vien commune, Gia Lam district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Building Hoa Sua kindergarten, Yen Vien commune, Gia Lam district" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 14

You did not use the site, Click here to remain logged. Timeout: 60 second