Bidder Selection Plan

Building Nha Be Vocational Training Center (Base 2)

  Watching    
Project Contractor selection plan Tender notice Bid award
Find: 08:48 21/03/2019
Contractor selection plan ID
20190351283-00
Publication date
08:48 21/03/2019
Publication status
Actual notification
Contractor selection plan name
Building Nha Be Vocational Training Center (Base 2)
Investor
KIEN NAM TRADING CONSTRUCTION INVESTMENT JOINT STOCK COMPANY
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20190351274-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval date
05/09/2017
Approval ID
1351/QĐ-SXD-KTXD
Related announcements

- Change: Notification form, Filter name, Lowest bid price, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 10
1.Consultancy and verification of construction drawing design and total cost estimate
Tender/ Prequalification Notice ID
Contract Period
30 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2017
Contract Type
All in one
Prequalification
No
2.Consultancy on design of construction drawings and total cost estimates
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2017
Contract Type
All in one
Prequalification
No
3.Bid preparation consultancy and bid evaluation (Consultancy bidding package for construction drawing design and total cost estimate; Construction supervision consultancy and equipment installation, Construction and installation bidding package, Equipment bidding package)
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2017
Contract Type
All in one
Prequalification
No
4.Construction of works + general items
Tender/ Prequalification Notice ID
Contract Period
500 days
Domestic/ International
International
Bidding method
Directly
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2018
Contract Type
According to fixed unit price
Prequalification
No
5.Device
Tender/ Prequalification Notice ID
Contract Period
500 days
Domestic/ International
International
Bidding method
Directly
Fields
Goods
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2018
Contract Type
According to fixed unit price
Prequalification
No
6.Static test of pile load
Tender/ Prequalification Notice ID
Contract Period
45 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2018
Contract Type
All in one
Prequalification
No
7.Construction supervision and equipment installation
Tender/ Prequalification Notice ID
Contract Period
500 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2018
Contract Type
All in one
Prequalification
No
8.Construction insurance
Tender/ Prequalification Notice ID
Contract Period
500 days
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2018
Contract Type
All in one
Prequalification
No
9.Construction settlement monitoring
Tender/ Prequalification Notice ID
Contract Period
500 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2018
Contract Type
All in one
Prequalification
No
10.Equipment cost appraisal
Tender/ Prequalification Notice ID
Contract Period
30 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2017
Contract Type
All in one
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Building Nha Be Vocational Training Center (Base 2)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Building Nha Be Vocational Training Center (Base 2)" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 86

You did not use the site, Click here to remain logged. Timeout: 60 second