Bidder Selection Plan

Component project 03: An Long residential cluster, An Long commune, Tam Nong district of Dong Thap province's residential layout project for the period 2021-2025

  Watching      
Find: 08:26 22/04/2024
Contractor Selection Plan ID
PL2300105537-01
Publishing time
08:25 22/04/2024
Posting Status
Published
Contractor selection plan name
Component project 03: An Long residential cluster, An Long commune, Tam Nong district of Dong Thap province's residential layout project for the period 2021-2025
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300028897-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Location
Authority that issues the decision
Ủy ban nhân dân tỉnh Đồng Tháp
Approval date
27/06/2023
Approval ID
Số 672/QĐ-UBND.HC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Bidding package number, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 7
1.Tender package No 01: Consulting survey, making construction technical plans and cost estimate for demining mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget capital for the period 2021-2025. The rest is local budget capital and other lawfully mobilized capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Tam Nông District, Đồng Tháp
2.Package 2: Geological survey consultancy after basic design
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget capital for the period 2021-2025. The rest is local budget capital and other lawfully mobilized capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Tam Nông District, Đồng Tháp
3.Package 03: Consulting on topographic survey and making construction design documents (step 2)
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Central budget capital for the period 2021-2025. The rest is local budget capital and other lawfully mobilized capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Tam Nông District, Đồng Tháp
4.Package 04: Consultancy and verification of BVTC design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget capital for the period 2021-2025. The rest is local budget capital and other lawfully mobilized capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Tam Nông District, Đồng Tháp
5.Tender package No 05: Equipment valuation consultancy
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget capital for the period 2021-2025. The rest is local budget capital and other lawfully mobilized capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Tam Nông District, Đồng Tháp
6.Package 06: Clearing bombs, mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget capital for the period 2021-2025. The rest is local budget capital and other lawfully mobilized capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Tam Nông District, Đồng Tháp
7.Package 07: Construction of technical, traffic and industrial infrastructure works (including construction equipment)
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Central budget capital for the period 2021-2025. The rest is local budget capital and other lawfully mobilized capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Location
Tam Nông District, Đồng Tháp

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Component project 03: An Long residential cluster, An Long commune, Tam Nong district of Dong Thap province's residential layout project for the period 2021-2025". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Component project 03: An Long residential cluster, An Long commune, Tam Nong district of Dong Thap province's residential layout project for the period 2021-2025" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 12

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8533 Projects are waiting for contractors
  • 449 Tender notices posted in the last 24 hours
  • 451 Contractor selection plan posted in the last 24 hours
  • 24888 Tender notices posted in the past month
  • 38664 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second