Component subproject selection plan: 110kV Hoa Phong 2 substation and connection under the Efficient Power Grid project in small and medium cities, using the German Government's ODA loan
Component subproject selection plan: 110kV Hoa Phong 2 substation and connection under the Efficient Power Grid project in small and medium cities, using the German Government's ODA loan
Open, international bidding without pre-qualification, not online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
According to fixed unit price
Prequalification
No
Location
2.CPC-KFW3.2-G02: Supply and transport first and second equipment, computer control system, information system 110kV Hoa Phong substation and connector
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
5.CPC-KFW3.2-HoaPhong-W01: Construction and testing, calibration, calculation and adjustment of relays, configuration installation, database building and SCADA signal testing of 110kV substation project Hoa Phong and connection
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
According to fixed unit price
Prequalification
No
Location
6.02/SCADA.A3-HoaPhong: Declare configuration, build a database at A3 and test signal from Control Center of Da Nang Electricity One Member Limited Liability Company with A3
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
7.03/SCADA.TTDK-HoaPhong: Declare configuration, build database at TTK and test signal from substation with Control Center of Da Nang Electricity One Member Limited Liability Company
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Component subproject selection plan: 110kV Hoa Phong 2 substation and connection under the Efficient Power Grid project in small and medium cities, using the German Government's ODA loan". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Component subproject selection plan: 110kV Hoa Phong 2 substation and connection under the Efficient Power Grid project in small and medium cities, using the German Government's ODA loan" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.