Bidder Selection Plan

Construction of Ban Khoang Kindergarten, Ngu Chi Son commune, Sa Pa town

  Watching      
Find: 11:38 29/04/2024
Contractor Selection Plan ID
PL2400039613-02
Publishing time
11:36 29/04/2024
Posting Status
Published
Contractor selection plan name
Construction of Ban Khoang Kindergarten, Ngu Chi Son commune, Sa Pa town
Investor
Ban QLDA đầu tư xây dựng thị xã Sa Pa
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300041378-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Location
Authority that issues the decision
UBND thị xã Sa Pa
Approval date
25/03/2024
Approval ID
666/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date (View changes)

- Change: Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 4
1.Tender package No 04: Construction work + fire protection equipment for Ban Khoang Kindergarten, Ngu Chi Son commune, Sa Pa town
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget investment in the National Target Program for socio-economic development in ethnic minority and mountainous areas in the period 2021-2025 + provincial budget + town budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Sa Pa District, Lào Cai
2.Tender package No 05: Supervision of construction works
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget investment in the National Target Program for socio-economic development in ethnic minority and mountainous areas in the period 2021-2025 + provincial budget + town budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Sa Pa District, Lào Cai
3.Tender package No 06: Fire protection construction supervision + Fire protection equipment installation
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget investment in the National Target Program for socio-economic development in ethnic minority and mountainous areas in the period 2021-2025 + provincial budget + town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Sa Pa District, Lào Cai
4.Package 07: Consultancy on inspection and acceptance work
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Central budget investment in the National Target Program for socio-economic development in ethnic minority and mountainous areas in the period 2021-2025 + provincial budget + town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Sa Pa District, Lào Cai

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Construction of Ban Khoang Kindergarten, Ngu Chi Son commune, Sa Pa town". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Construction of Ban Khoang Kindergarten, Ngu Chi Son commune, Sa Pa town" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 8

You did not use the site, Click here to remain logged. Timeout: 60 second