Bidder Selection Plan

Construction of Hall, Internal Road and 03 Negative Pressure Rooms at Lam Dong II Hospital

  Watching      
This Contractors Selection Plan data is found on both the old and new Public Procurement systems. The data you are viewing is updated from the new Public Procurement system
Find: 17:01 11/08/2021
Contractor Selection Plan ID
20210828522-00
Publishing time
16:56 11/08/2021
Posting Status
Published
Contractor selection plan name
Construction of Hall, Internal Road and 03 Negative Pressure Rooms at Lam Dong II Hospital
Bid Solicitor
Project management forms
Another form
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210828512-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Location
Authority that issues the decision
N/A
Approval date
10/08/2021
Approval ID
2073/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 1
1.Package 10: Procurement of furniture for the Hall
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget plan in 2021, allocate 11,000 million VND (According to Decision No. 886/QD-UBND dated April 6, 2021 of the Provincial People's Committee)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Construction of Hall, Internal Road and 03 Negative Pressure Rooms at Lam Dong II Hospital". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Construction of Hall, Internal Road and 03 Negative Pressure Rooms at Lam Dong II Hospital" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 110

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8280 Projects are waiting for contractors
  • 1105 Tender notices posted in the last 24 hours
  • 1781 Contractor selection plan posted in the last 24 hours
  • 24321 Tender notices posted in the past month
  • 38539 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second