Bidder Selection Plan

Construction of housing for poor ethnic minority households in MePu commune, Duc Linh district

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 13:08 30/10/2024
Contractor Selection Plan ID
PL2400251516-00
Publishing time
13:07 30/10/2024
Posting Status
Published
Contractor selection plan name
Construction of housing for poor ethnic minority households in MePu commune, Duc Linh district
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Spending Category
Investment and Development Spending
Location
Authority that issues the decision
UBND xã Mê Pu
Approval date
04/05/2024
Approval ID
81/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 1
1.Construction of housing for poor ethnic minority households in MePu commune, Duc Linh district
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Capital source details
District Fund for the Poor and national target program capital for 2022-2023
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
May 2024
Type of contract
All in One
Prequalification
No
Location
Đức Linh District, Bình Thuận

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Construction of housing for poor ethnic minority households in MePu commune, Duc Linh district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Construction of housing for poor ethnic minority households in MePu commune, Duc Linh district" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second