Bidder Selection Plan
Construction of Tan Van Kindergarten
Contractor selection plan ID
20210938566-00
Publication date
15:12 16/09/2021
Publication status
Actual notification
Contractor selection plan name
Construction of Tan Van Kindergarten
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210938456-00
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
QD phe duyet KHLCNT MN TAN VAN-7582-QD-UBND-13092021.pdf
List of Bid:
Number of packages: 17
1. Consulting for designing BVTC-DT
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
2. Consulting and design verification BVTC-DT
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
3. Construction + Substation
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
4. Construction of fire protection system + automatic fire alarm
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
6. Consultancy on preparation of bidding documents, evaluation of bids for design bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
7. Consulting on appraisal of bidding documents, results of contractor selection for design bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
8. Consulting on making bidding documents, evaluating bids for construction and installation bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
9. Consultancy on appraisal of bidding documents, selection of contractors for construction and installation bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
10. Consulting on making bidding documents, evaluating bids for equipment packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
11. Consultancy on appraisal of bidding documents, results of contractor selection for equipment packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
12. Consulting on planning for environmental protection
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
13. Consultancy on verifying tasks and outline of environmental protection plan
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2021
14. Consultancy on verifying cost estimates of construction works inspection and acceptance
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
15. Equipment appraisal consulting
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Two Stages Single Envelope
Contractor Selection Period
Q2 2022
16. Construction insurance
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
City budget. Bien Hoa
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Construction of Tan Van Kindergarten". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email