Bidder Selection Plan

Contractor selection plan

  Watching      
Find: 09:50 11/03/2023
Contractor Selection Plan ID
PL2300029222-00
Publishing time
09:49 11/03/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan
Bid Solicitor
Investment objective
Invest in building commune police headquarters under the Project on Commune-level Police Headquarters being built by Hai Duong province, creating working conditions for the police forces of communes, serving the crime prevention work. , maintain social order and safety
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300009366-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Authority that issues the decision
Ủy ban nhân dân xã Ngũ Phúc
Approval date
08/03/2023
Approval ID
61/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 8
1.Tender package No 5: Compression testing of concrete piles
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
Timed and Adjusted Unit Price
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
2.Tender package No 7: Audit of works
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
All in One
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
3.Package 3: Project management consulting
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
All in One
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
4.Tender package No 1: Consulting for E-HSMT preparation; E-HSDT review
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
All in One
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
5.Tender package No 6: Construction Insurance
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
All in One
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
6.Tender package No 4: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
All in One
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
7.Tender package No 2: E-HSMT appraisal consultancy and LCNT . results
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
Timed and Adjusted Unit Price
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
8.Tender package No 8: Construction work
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2023
Type of contract
All in One
Implementation location
Kim Thành District, Province Hải Dương
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 23

You did not use the site, Click here to remain logged. Timeout: 60 second