Contractor Selection Plan ID
PL2300047728-00
Publishing time
09:15 10/04/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan
Investment objective
Contributing to the improvement of infrastructure to strive for the district to meet new rural standards. In order to well implement the propaganda of the Party's guidelines and policies, the State's policies and laws to the people and develop the cause of culture, sports and tourism in the district.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300014098-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
UBND huyện Tam Đường
Approval date
30/12/2022
Approval ID
4875/QĐ-UBND ngày 30/12/2022
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 8
1.Package 06 (Anti-termite works)
Tender/ Prequalification Notice ID
Contract execution period
6 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province
2.Package 01: Consulting survey, making economic - technical reports
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2022
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province
3.Bidding package for consulting and verifying BVTC design - estimate
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
December, 2022
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province
4.Tender package No 05 (Construction supervision consultant + equipment)
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province
5.Package number 07 (construction + equipment)
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province
6.Package 02 (Consultancy on setting up bidding documents for construction and installation bidding package + equipment)
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province
7.Tender package No 03 (Construction insurance)
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province
8.Package 04 (Construction quality inspection)
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Sources of the national target program on new rural construction and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tam Đường District, Lai Châu
Implementation location (Before merge)
Lai Chau province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 10

You did not use the site, Click here to remain logged. Timeout: 60 second