Bidder Selection Plan

Contractor selection plan (2nd time) component project No. 1: Water source control works for Nguyen Tan Thanh canal under the project of water control works for Nguyen Tan Thanh canal and the right bank of Vam Co Tay river

  Watching      
Find: 21:47 13/09/2022
Contractor selection plan ID
20220937339-00
Publication date
21:42 13/09/2022
Publication status
Actual notification
Contractor selection plan name
Contractor selection plan (2nd time) component project No. 1: Water source control works for Nguyen Tan Thanh canal under the project of water control works for Nguyen Tan Thanh canal and the right bank of Vam Co Tay river
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20220633908-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
06/09/2022
Approval ID
3373/QĐ-BNN-XD
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

Related announcements

- Change: Notification Type, Notification form, Classify, Bidding package number, Lowest bid price, Highest bid price, Decision-making agency, Publication date, Bidding package information (View changes)

- Change: Bidding package number, Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 9
1.Construction supervision; Prepare bidding documents and evaluate bids for consultancy, construction and installation bidding packages
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Do it yourself, domestically, without pre-qualification, not online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
By the time
Prequalification
No
Location
2.Supervising the clearance of mines and explosives
Tender/ Prequalification Notice ID
Contract Period
3 months
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
3.Supervision of production and installation of equipment, gate and gate valves Nguyen Tan Thanh
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Contract Type
All in one
Prequalification
No
Location
4.Survey, determine new cost estimates, adjusted cost estimates
Tender/ Prequalification Notice ID
Contract Period
18 months
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
5.Environmental monitoring and monitoring (implementing environmental commitments)
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Contract Type
All in one
Prequalification
No
Location
6.Set up operating procedures for the system
Tender/ Prequalification Notice ID
Contract Period
6 months
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
3rd Quarter of 2023
Contract Type
All in one
Prequalification
No
Location
7.Package XL01: Construction, supply and installation of Nguyen Tan Thanh sewer equipment
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to the adjusted unit price
Prequalification
No
Location
8.Construction of clearing mines and explosives
Tender/ Prequalification Notice ID
Contract Period
3 months
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to fixed unit price
Prequalification
No
Location
9.Construction insurance
Tender/ Prequalification Notice ID
Contract Period
24 months
Domestic/ International
International
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget capital managed by the Ministry of Agriculture and Rural Development
Contractor Selection Type
Competitive offers, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (2nd time) component project No. 1: Water source control works for Nguyen Tan Thanh canal under the project of water control works for Nguyen Tan Thanh canal and the right bank of Vam Co Tay river". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (2nd time) component project No. 1: Water source control works for Nguyen Tan Thanh canal under the project of water control works for Nguyen Tan Thanh canal and the right bank of Vam Co Tay river" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 120

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 7979 Projects are waiting for contractors
  • 231 Tender notices posted in the last 24 hours
  • 321 Contractor selection plan posted in the last 24 hours
  • 23722 Tender notices posted in the past month
  • 37264 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second