Bidder Selection Plan

Contractor selection plan Compensation plan for moving pumping stations to serve site clearance for the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to the road province 394

  Watching      
Find: 16:45 01/11/2024
Contractor Selection Plan ID
PL2400252755-00
Publishing time
16:44 01/11/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan Compensation plan for moving pumping stations to serve site clearance for the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to the road province 394
Investment objective
Moving the pumping station within the scope of site clearance to serve the project: Renovating and upgrading provincial road 395 (section from km16+750 -km23+920) and the road leading to Cay bridge to provincial road 394
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400064063-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
5 Years
Authority that issues the decision
Uỷ ban nhân dân huyện Bình Giang
Approval date
30/10/2024
Approval ID
2671/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 6
1.Tender package No 01: Consulting on making bidding documents, evaluating construction bids
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents, evaluate construction bids
Capital source details
Source of site clearance costs for the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to provincial road 394, Binh Giang district
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Bình Giang District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
2.Package 02: Consultancy on appraisal of bidding documents, dossier of requirements, appraisal of contractor selection results
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Evaluation of bidding documents, dossiers of requirements, appraisal of contractor selection results
Capital source details
Source of site clearance costs for the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to provincial road 394, Binh Giang district
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Bình Giang District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
3.Tender package No 03: Consulting on construction supervision and equipment installation supervision
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision and equipment installation supervision
Capital source details
Source of site clearance costs for the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to provincial road 394, Binh Giang district
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Bình Giang District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
4.Package 04: Independent audit consultant
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit of completed project settlement reports
Capital source details
Capital source in site clearance costs of the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to provincial road 394.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Bình Giang District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
5.Tender package No 05: Static compression of experimental piles
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Compression of experimental concrete piles
Capital source details
Capital source in site clearance costs of the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to provincial road 394.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Bình Giang District, Province Hải Dương
Implementation location (After merge)
Prequalification
No
6.Package 06: Construction and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and equipment installation
Capital source details
Construction and equipment installation
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Bình Giang District, Province Hải Dương
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan Compensation plan for moving pumping stations to serve site clearance for the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to the road province 394". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan Compensation plan for moving pumping stations to serve site clearance for the project to renovate and upgrade provincial road 395 (section from Km16+750 - Km23+920) and bridge path to the road province 394" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 9

You did not use the site, Click here to remain logged. Timeout: 60 second