Bidder Selection Plan

Contractor selection plan (continued) Lighting system project in Binh An commune

  Watching      
Find: 14:54 02/07/2026
Contractor Selection Plan ID
PL2600196037-00
Publishing time
14:49 02/07/2026
Posting Status
Published
Contractor selection plan name
Contractor selection plan (continued) Lighting system project in Binh An commune
Investment objective
The project is carried out for the purpose of traffic safety for people and vehicles when participating in traffic: + Convenient for people to travel on the road. + Helps traffic on the road achieve a higher level of safety at night, reduces traffic accidents in the area, and avoids loss of life and property for the people.
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600042094-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Văn phòng HĐND-UBND
Approval date
30/06/2026
Approval ID
51/QD-VP
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 5
1.Tender package No 04 (Construction): construction and installation
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of lighting system project in Binh An commune
Capital source details
Town budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
2.Tender package No 05 (Consulting): Construction supervision of Tender package No 04
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction package No. 04
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
3.Bidding package No. 06 (consulting): Prepare E-Bidding Documents, evaluate E-Bidding Documents for bidding package No. 04
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
E-HSMT, E-HSDT Package No. 04
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
4.Bidding package No. 07 (consulting): Appraisal of E-HSMT, appraisal of contractor selection results for bidding package No. 04
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Evaluation E-HSMT, appraisal results of contractor selection package No. 04
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
5.Tender package No 08 (Non-consulting): Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
485 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (continued) Lighting system project in Binh An commune". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (continued) Lighting system project in Binh An commune" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 7

You did not use the site, Click here to remain logged. Timeout: 60 second