Bidder Selection Plan

Contractor selection plan (correction) Quang Trach 1 . Thermal Power Plant Project

  Watching      
Find: 10:07 31/05/2023
Contractor Selection Plan ID
PL2200067833-02
Publishing time
10:05 31/05/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan (correction) Quang Trach 1 . Thermal Power Plant Project
Bid Solicitor
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2200019802-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Project implementation time
5 Years
Authority that issues the decision
Tập đoàn Điện lực Việt Nam
Approval date
20/05/2020
Approval ID
101/QĐ-EVN
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Investor, Total investment, Lowest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Investor, Publication date (View changes)

- Change: Investor, Lowest bid price, Highest bid price, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 14
1.Package 9 (XL01-QT1): Construction of the operation house and housing for employees performing the task of operating Quang Trach I Thermal Power Plant
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
June, 2020
Type of contract
According to adjusted unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
2.Tender package No 13 (XL03-QT1): BVTC design - fabrication and installation of steel structure roof of coal warehouse and windscreen wall of coal warehouse
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
December, 2021
Type of contract
All in One
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
3.Package 14 (XL04-QT1 + Infrastructure): Construction of slag dump, water collection tower, return water pipe and traffic route to Quang Trach Power Center from Hon La Economic Zone
Tender/ Prequalification Notice ID
Contract execution period
20 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
November, 2021
Type of contract
Fixed unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
4.Package 17 (XL06-QT1): Construction of administrative and auxiliary buildings
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
March, 2022
Type of contract
Fixed unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
5.Tender package No 18 (XL07-QT1): Construction of landscape items
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2022
Type of contract
All in One
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
6.Tender package No 19 (MS01-QT1): Fabrication and supply of pipes for receiving and discharging cooling water
Tender/ Prequalification Notice ID
Contract execution period
16 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
January, 2022
Type of contract
Fixed unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
7.Tender package No 23 (GD01-QT1): Inspection of imported coal and DO oil for trial run
Tender/ Prequalification Notice ID
Contract execution period
14 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
Fixed unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
8.Tender package No 24 (GD02-QT1): Inspection of materials and equipment
Tender/ Prequalification Notice ID
Contract execution period
46 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September, 2021
Type of contract
Fixed unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
9.Package 12 (TV09-QT1): Auditing and finalizing the completed investment capital of Quang Trach I Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
42 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
September, 2021
Type of contract
All in One
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
10.Package 20 (MS02-QT1): Supplying DO oil for test run
Tender/ Prequalification Notice ID
Contract execution period
16 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
July 2023
Type of contract
According to adjusted unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
11.Tender package No 21 (MS03-QT1): Supplying imported coal for trial run
Tender/ Prequalification Notice ID
Contract execution period
16 months
Domestic/ International
International
Bidding method
Directly
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
July 2023
Type of contract
According to adjusted unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
12.Package 26 (BH03-QT1): Construction insurance and civil liability insurance for third parties during the construction of the main factory
Tender/ Prequalification Notice ID
Contract execution period
72 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
January, 2021
Type of contract
Fixed unit price
Prequalification
No
13.Package 16 (XL05-QT1): Construction of the cooling water channel from the receiving gate to the StopLog of the cooling water pump station.
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
March, 2022
Type of contract
Fixed unit price
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No
14.Package 22 (BH01-QT1): Construction insurance and civil liability insurance for third parties during the construction of a number of work items under the Quang Trach thermal power plant project I
Tender/ Prequalification Notice ID
Contract execution period
0 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVN's capital and domestic commercial loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November, 2021
Type of contract
All in One
Implementation location
Quảng Trạch District, Province Quảng Bình
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (correction) Quang Trach 1 . Thermal Power Plant Project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (correction) Quang Trach 1 . Thermal Power Plant Project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 61

You did not use the site, Click here to remain logged. Timeout: 60 second