Bidder Selection Plan

Contractor selection plan (Design and construction phase implemented after the project is approved) Project: Upgrading hot asphalt concrete for rural commune roads including Cay Truong II route - 08, 12, 42, 43, 46, 50, 54, 60, 100 and branch routes.

  Watching      
Find: 08:22 24/07/2026
Contractor Selection Plan ID
PL2600225934-01
Publishing time
08:21 24/07/2026
Posting Status
Published
Contractor selection plan name
Contractor selection plan (Design and construction phase implemented after the project is approved) Project: Upgrading hot asphalt concrete for rural commune roads including Cay Truong II route - 08, 12, 42, 43, 46, 50, 54, 60, 100 and branch routes.
Investment objective
Upgrading hot asphalt concrete on commune rural roads including Cay Truong II route - 08, 12, 42, 43, 46, 50, 54, 60, 100 and branch routes. Create a driving force to promote socio-economic development, trade - services, agricultural and industrial production in Tru Van Tho commune and surrounding areas. Contribute to perfecting the transportation system, serving the national target program of building advanced new rural areas, moving towards model new rural areas.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600041559-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng xã Trừ Văn Thố
Approval date
22/07/2026
Approval ID
73/QĐ-BQLDA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 8
1.Consulting on setting up bidding documents, evaluating bids for construction and installation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Make the Bidding Documentation, evaluate the Bidding for construction and installation
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
2.Consulting on appraisal of bidding documents, appraisal of contractor selection results for construction and installation packages
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out appraisal of bidding documents and appraisal of contractor selection results for construction and installation packages
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
3.Civil Works
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Deploy construction work
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
4.Consulting on setting up bidding documents, evaluating bids for supervision consultancy bidding packages
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents and evaluate bidding documents for supervision consulting packages
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
5.Consulting on appraisal of bidding documents, appraisal of contractor selection results for supervision consulting packages
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out appraisal of bidding documents and appraisal of contractor selection results for supervision consulting packages
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
6.Construction supervision consultant
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out monitoring of quality, progress, and safety in construction according to the approved design
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
7.Cost of construction works
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Providing construction insurance services during construction
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
8.Cost audit
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out inspection and review of documents for validity before settlement
Capital source details
Targeted support capital from Ho Chi Minh City budget for commune budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the second quarter, 2027
Type of contract
All in One
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (Design and construction phase implemented after the project is approved) Project: Upgrading hot asphalt concrete for rural commune roads including Cay Truong II route - 08, 12, 42, 43, 46, 50, 54, 60, 100 and branch routes.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (Design and construction phase implemented after the project is approved) Project: Upgrading hot asphalt concrete for rural commune roads including Cay Truong II route - 08, 12, 42, 43, 46, 50, 54, 60, 100 and branch routes." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 5

You did not use the site, Click here to remain logged. Timeout: 60 second