Bidder Selection Plan

Contractor selection plan for Fixed Asset Repair Project - VKT in 2026 (part of repairing concrete yards and roads in ground area +35)

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 15:34 12/01/2026
Contractor Selection Plan ID
PL2600007263-00
Publishing time
15:25 12/01/2026
Posting Status
Published
Contractor selection plan name
Contractor selection plan for Fixed Asset Repair Project - VKT in 2026 (part of repairing concrete yards and roads in ground area +35)
Procurement name
Fixed Asset Repair Project - VKT in 2026 (Repair of concrete yard and road in ground area +35)
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Shopping budget
To view full information, please Login or Register
Spending Category
Mandatory spending
Authority that issues the decision
CHI NHÁNH TẬP ĐOÀN CÔNG NGHIỆP THAN – KHOÁNG SẢN VIỆT NAM - CÔNG TY THAN QUANG HANH - TKV
Approval date
09/01/2026
Approval ID
Số 190/QĐ-VQHC-ĐTM
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 3
1.Tender package No 1: Supervision of construction and repair of concrete yards and roads in ground area +35
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction supervision of parts of the repair plan
Capital source details
Production and business expenses of Quang Hanh Coal Company - TKV
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Tender package No 2: Construction and repair of concrete yards and roads in site area +35
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction work under the repair plan
Capital source details
Production and business expenses of Quang Hanh Coal Company - TKV
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
3.Package 3: Construction audit
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Implementing the audit of the plan for capital settlement
Capital source details
Production and business expenses of Quang Hanh Coal Company - TKV
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for Fixed Asset Repair Project - VKT in 2026 (part of repairing concrete yards and roads in ground area +35)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for Fixed Asset Repair Project - VKT in 2026 (part of repairing concrete yards and roads in ground area +35)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 1

You did not use the site, Click here to remain logged. Timeout: 60 second