Bidder Selection Plan

Contractor selection plan for O Mon III Thermal Power Plant Project

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 17:21 06/08/2026
Contractor Selection Plan ID
PL2600040908-02
Publishing time
15:08 06/08/2026
Posting Status
Published
Contractor selection plan name
Contractor selection plan for O Mon III Thermal Power Plant Project
Investment objective
Construction of 01 combined cycle gas turbine thermal power plant, capacity of about MW ± 15%, to provide a stable power source for the Southern region in particular and the National power system in general, contributing to ensuring energy security and safety of the power system.
Project management forms
BQLDA major - area
Using ODA capital?
Have
Funding source
ODA capital
Project number
PR2600004407-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Project implementation time
5 Years
Authority that issues the decision
Tập đoàn Công nghiệp - Năng lượng Quốc gia Việt Nam
Approval date
31/07/2026
Approval ID
6556/QĐ-CNNL
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 9
1.OM3-GTG-HHO-03.1: Design and supply of Gas Turbine and Gas Turbine Generator (GTG) cluster for O Mon III Thermal Power Plant (GTG Package under O Mon III Thermal Power Plant Project)
Tender/ Prequalification Notice ID
Contract execution period
39 months
Domestic/ International
International
Bidding method
Directly
Fields
Uncategoried
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Design, manufacture, and supply Gas Turbine and Gas Turbine Generator (GTG) clusters at O Mon III Thermal Power Plant, including: - Includes accompanying services such as providing technical assistance (TA) experts for installation, commissioning, and acceptance.
Capital source details
Equity capital, Japanese loan capital (JICA,..) and commercial loan capital
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Implementation location
Phường Phước Thới, City Cần Thơ
Prequalification
No
2.OM3-GEN-CAR-04: Insurance for all risks during the construction, installation, testing and acceptance of O Mon III Thermal Power Plant
Tender/ Prequalification Notice ID
Contract execution period
58 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Providing insurance services during the process of construction, installation, and commissioning of the O Mon III Thermal Power Plant project, except for professional liability insurance of consultants under the contractor's responsibility
Capital source details
Equity and commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter IV, 2026
Type of contract
By percentage
Implementation location
Phường Phước Thới, City Cần Thơ
Prequalification
No
3.OM3-PMC-TVA-05: Consulting and project management support for O Mon III Thermal Power Plant Project (PMC Consulting)
Tender/ Prequalification Notice ID
Contract execution period
43 months
Domestic/ International
International
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Construction Survey Supervision Consulting, Construction Execution and Construction Installation; - Consulting and supporting project management; - Consulting on technical design verification.
Capital source details
Equity capital, Japanese loan capital (JICA, ..) and commercial loan capital
Contractor Selection Type
Restricted Match
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
In the third quarter, 2026
Type of contract
Timed
Implementation location
Prequalification
No
4.OM3-FIN-TVA-06: Legal advice for the borrower of O Mon III Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
50 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Support the Investor within the scope of work including, but not limited to the following: - Advise and support the Borrower in developing a negotiating position, reviewing and commenting on the Financial Documents throughout the negotiation process with Lenders and their legal consultants; - Provide legal reports to the Investor in accordance with applicable laws for the final version of the Financial Documents and the entire transaction, including evaluating the legality, validity, binding and enforceability of the Financial Documents, as well as other related legal issues in accordance with applicable laws; - Drafting key loan terms and conditions; - Review, negotiate and complete loan contracts; - Review, negotiate and complete fee payment agreements and other related credit documents; - Support PVN in preparing, negotiating and completing the prerequisites of loans; provide legal opinions related to PVN's signing of credit documents in case of request from the Lender; - Support procedures for disbursement; - Perform other tasks as requested by PVN in accordance with the scope and nature of the bidding package.
Capital source details
Equity and commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
5.OM3-EIA-TVA-07: Consulting on environmental monitoring and supervision during the construction process of O Mon III Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
36 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Monitoring and sampling background data (data from 2 seasons), comparing with current standards to evaluate the current environmental status; Periodic environmental monitoring every 3 months during Project construction (including the affected area surrounding the Project); Monitor and evaluate occupational safety and hygiene at the Project; Monitor, evaluate and report on the process of collection, transportation, and treatment of generated waste (including solid waste, hazardous waste, and household waste) during the construction phase; Proposing measures to improve and minimize environmental impacts during construction; Submit environmental protection reports to competent management agencies in compliance with the approved EIA Report, Environmental Protection Law, Construction Law and related legal documents.
Capital source details
Equity and commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Phước Thới, City Cần Thơ
Prequalification
No
6.OM3-GEN-TVA-08: Independent monitoring of construction displacement and deformation during construction of O Mon III Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
33 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Monitoring of displacement and deformation of works in the process of construction and existing works from the initial cycle (cycle 0) before the load, impact changes to the foundation, foundation, construction structure
Capital source details
Equity and commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter IV, 2026
Type of contract
All in One
Implementation location
Phường Phước Thới, City Cần Thơ
Prequalification
No
7.OM3-GEN-TVA-09: Consulting on the Law on Legal Support for the Investor during the implementation of the O Mon III Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
43 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Consulting on the negotiation and completion of the Main Factory EPC Contract - Consulting during project implementation - Consulting on Shared Facilities Agreement (SFA) - Consulting on decentralization and authorization of the Investor - Consulting on legal regulations and the impact of changes in regulations related to the Project.
Capital source details
Equity and commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
8.OM3-AUD-TVA-10: Consulting on auditing construction investment capital of O Mon III Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
36 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Auditing the legal records of the project, auditing investment capital sources of the project, auditing investment costs, auditing investment expenses not included in the value of asset (if any), audit to determine the value of assets, auditing determining debt, supplies and equipment, considering the implementation of the conclusions of the inspection, examination, review, and submission to the investor's petition.
Capital source details
Equity and commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter IV, 2027
Type of contract
All in One
Implementation location
Prequalification
No
9.Design, procurement, construction and installation, testing, and acceptance of the Ô Môn III Power Plant project.
Tender/ Prequalification Notice ID
Contract execution period
44 months
Domestic/ International
International
Bidding method
Directly
Fields
Uncategoried
Regulatory compliance
Is different
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey, design, procurement, construction and installation, testing, acceptance, and handover of the Ô Môn III Thermal Power Plant (including all work scope of the "Design, Supply of Gas Turbine and Gas Turbine Generator Set (GTG) for Ô Môn III Thermal Power Plant" package approved under Decision No. 1152/QD-CNNL dated February 9, 2026 by the Petrovietnam Board of Members).
Capital source details
Owner's equity, Japanese loans, and commercial loans
Contractor Selection Type
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Phước Thới, City Cần Thơ
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for O Mon III Thermal Power Plant Project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for O Mon III Thermal Power Plant Project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 15

You did not use the site, Click here to remain logged. Timeout: 60 second