Bidder Selection Plan

Contractor selection plan for O Mon IV Thermal Power Plant Project

  Watching      
Find: 13:05 20/09/2024
Contractor Selection Plan ID
PL2400205347-00
Publishing time
12:05 20/09/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for O Mon IV Thermal Power Plant Project
Bid Solicitor
Investor
Investment objective
Construction of a combined cycle gas turbine thermal power plant with a capacity of about 1,050 MW ± 10%.
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400053350-00
Name of project
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Project implementation time
5 Years
Authority that issues the decision
TẬP ĐOÀN DẦU KHÍ VIỆT NAM
Approval date
23/08/2024
Approval ID
6102/QĐ-DKVN
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Approval date, Approval ID, Publication date (View changes)

- Change: Investor, Decision-making agency, Approval date, Approval ID, Publication date (View changes)

- Change: Publication date (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Filter name, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 18
1.OM4-EPC-HHO-06: Design, procurement, construction, installation, commissioning and acceptance of O Mon IV Thermal Power Plant
Tender/ Prequalification Notice ID
Contract execution period
34 months
Domestic/ International
International
Bidding method
Directly
Fields
Uncategoried
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey, Design, Procurement, Construction, Installation, Commissioning, Acceptance and Handover of O Mon IV Thermal Power Plant, which does not include the scope of work under bidding packages No. OM4-BOP-TVA-08 and OM4-BOP-HHO-09.
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
2.OM4-EPC-TVA-07: Consulting on estimate verification of EPC bidding package for Main Plant under O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting on cost estimate verification of EPC Package for Main Plant under O Mon IV Thermal Power Plant Project
Capital source details
Owners and Loans
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
3.OM4-BOP-TVA-08: Survey, design construction drawings and prepare estimates for the Administrative Building and some ancillary items of the O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
10 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey, design construction drawings and prepare estimates for shared roads (Including surface water drainage system), Administration building, Dining room, 2-wheel garage, 4-wheel garage, landscape completion Shared green trees belong to the O Mon IV Thermal Power Plant Project
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
Package and Fixed Price
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
4.OM4-BOP-HHO-09: Construction, supply and installation of equipment for the Administration Building and some auxiliary items of the O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
22 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Uncategoried
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction, supply and installation of equipment for shared roads (Including surface water drainage system), Administration building, Restaurant, 2-wheel drive garage, 4-wheel drive garage, completing the green landscape of the area shared use under O Mon IV Thermal Power Plant Project
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
5.OM4-GEN-TVA-10: Consulting on verification of construction design implemented after basic design of O Mon IV Thermal Power Plant project
Tender/ Prequalification Notice ID
Contract execution period
8 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verifying the technical design of the main factory EPC package; - Verify construction drawing design (step 2, after basic design) and construction estimates for items under package OM4-BOP-TVA-08
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
6.OM4-GEN-CAR-11: Insurance for all risks during construction, installation, test run and acceptance of O Mon IV Thermal Power Plant project
Tender/ Prequalification Notice ID
Contract execution period
58 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Providing insurance services during the construction, installation, and acceptance testing of the O Mon IV Thermal Power Plant project, including all of the following packages: OM4-EPC-HHO-06; OM4-BOP-HHO-09 except for professional liability insurance of consultants under contractor liability of the above bidding packages
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
By percentage
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
7.OM4-PMC-TVA-12: Project management support consulting for O Mon IV Thermal Power Plant Project (PMC)
Tender/ Prequalification Notice ID
Contract execution period
41 months
Domestic/ International
International
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
(1) Construction Survey Supervision Consulting, Construction and Construction Installation Consultancy: Survey supervision consulting, construction supervision, project installation including quality, progress, block quality, environmental health safety and related work at the construction site of all construction, construction and installation works of the bidding packages OM4-EPC-HHO-06 and OM4- BOP-HHO-09; Supervise the production, manufacturing, and testing of equipment/materials according to the ITP approved by the Investor; Coordinate with the Technical Consulting department to support the Investor in monitoring safety and environmental health during the factory acceptance test run; Carry out work related to payment, settlement of bidding packages, settlement of completed projects according to regulations; Prepare periodic reports, advise on handling issues related to quality, progress, volume, environmental health and safety at the site... (2) Consulting section to support project management : Technical support in LCNT EPC; Review, verify/evaluate (Verification) Technical design documents; Review, verify and approve construction drawing designs as a basis for approval by the Investor; Assist in reviewing technical documents for procurement, manufacturing, and testing; Participate in witnessing testing at the factory (if required); Technical support in installation and commissioning; Review and approve relevant technical documents such as O&M, QRA, connection, fire protection, control... Review and approve technical documents submitted by the General Contractor; Support the Investor with relevant issues during project implementation.
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
Package and Timed
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
8.OM4-GEN-TVA-13: Consulting on establishing scope of work, bidding package estimates for bidding packages OM4-PMC-TVA-12 and OM4-EIA-TVA-17 and OM4-GEN-TVA-18
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting on establishing scope of work and estimates for bidding packages Consulting and supporting project management; Environmental monitoring/monitoring; Monitoring displacement and deformation of works during the construction process
Capital source details
Owners and Loans
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
9.OM4-GEN-TVA-14: Consulting on Verification of Bidding Package Estimates for bidding packages OM4-PMC-TVA-12 and OM4-IEA-TVA-17 and OM4-GEN-TVA-18
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verify the Package Estimates of the OM4-PMC-TVA-12, OM4-IEA-TV17 and OM4-GEN-TVA-18 packages for appraisal and approval according to regulations.
Capital source details
Owners and Loans
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
10.OM4-ESIA-TVA-15: Consulting on assessing differences between the approved Environmental Impact Assessment and international standards for capital arrangement of O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Collect and research EIA documents (and project documents); review and identify differences and additional requirements between the contents of the EIA and the World Bank's Environmental and Social Policy Framework (ESF) or review and identify differences and additional requirements between the the content of the EIA and IFC's Environmental and Social performance standards and finally determining the scope of work (SOW), estimates, terms of reference (TOR) for the implementation of ESIA (bid package no. OM4 -ESIA-TVA-16 Consulting on preparing a Social Environmental Impact Assessment Report according to international standards to serve capital arrangements) according to the standards and requirements of donors
Capital source details
Owner
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
11.OM4-ESIA-TVA-16: Consulting on preparing a Social Environmental Impact Assessment Report according to international standards to serve capital arrangement for O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
International
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Based on the products of the OM4-ESIA-TVA-15 bidding package, the assessment of social environmental impacts according to international standards (IFC and WB) includes determining the scope of the project, collecting the basis environmental data, socio-economic data, determination of environmental impact assessment and mitigation measures, with great emphasis on human, social factors and disadvantaged groups; Biodiversity assessment (if any), social and health impact assessment, traffic impact, community consultation and socio-environmental action plan (ESAP), socio-environmental management plan (ESMP) during the construction and operation phase
Capital source details
Owner
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
12.OM4-EIA-TVA-17: Consulting on environmental monitoring and supervision during the construction process of O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
34 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Monitoring and sampling, comparing with current standards to evaluate the current environmental status; Evaluate the process of collecting and transporting generated waste; Proposing to enhance and improve environmental efficiency during construction; Submit environmental protection reports to competent management agencies in compliance with approved EIA, Environmental Protection Law, Construction Law and related legal documents.
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
13.OM4-GEN-TVA-18: Independent monitoring of displacement and deformation during construction and warranty period of O Mon IV Thermal Power Plant project
Tender/ Prequalification Notice ID
Contract execution period
33 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Monitoring displacement and deformation of works during construction and adjacent existing works since the initial cycle (cycle 0) before there are loads and impact changes on the foundation. , building structure
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
14.OM4-GEN-TVA-19: Consulting on the Law on Legal Support for Investors during the implementation of O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
43 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting on the negotiation and completion phase of the Main Factory EPC Contract - Consulting during Project implementation - Consulting on Shared Items Agreement (SFA) - Consulting on decentralization and delegation Rights of the Investor - Consulting on legal regulations and the impact of changes in regulations related to the Project.
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
Timed
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Can Tho city
15.OM4-FIN-TVA-20: Legal advice for the Borrower of O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
43 months
Domestic/ International
International
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Advise and assist the Borrower in developing negotiating positions and reviewing opinions on the Financial Documents throughout the negotiation process with ECAs/Lenders and their legal advice. Provide legal reports to the Investor in accordance with the laws applicable to the final version of the Financial Documents and the entire Transaction including the legality, validity, binding effect and enforceability of the Documents Financing and any other related matters in accordance with applicable laws. And the following tasks: (i) Drafting the main loan terms and conditions; (ii) Review, negotiate and complete loan contracts; (iii) Review, negotiate and complete fee payment agreements and other related credit documents; (iv) Support PVN in preparing, negotiating and completing prerequisites of loans, providing legal opinions related to PVN's signing of credit documents in case the lender requires bridge. (v) Other tasks arising at PVN's request/due to assumptions for the scope of work that are no longer consistent with reality.
Capital source details
Owner
Contractor Selection Type
Restricted Match
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
Timed
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
16.OM4-HTA-PTV-21: Services to protect premises and field assets from reception to handover to the EPC Contractor of the main plant of O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Providing asset protection services at the scene and construction site premises from the time of receiving handover from EVN until handing over to the EPC General Contractor of the main factory to take over management according to the provisions of the signed Contract.
Capital source details
Owners and Loans
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
17.OM4-AUD-TVA-22: Consulting on auditing construction investment capital of O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
36 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Auditing legal documents of the Project, Auditing the investment capital of the Project, Auditing investment costs, Auditing investment costs not included in asset value (if any), Auditing valuation Asset value, Audit to determine outstanding debts, supplies and equipment, Review the implementation of conclusions of inspection and examination agencies, Consider and submit to competent authorities to resolve the Owner's recommendations private.
Capital source details
Owners and Loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city
18.OM4-FIN-TVA-23: Financial consulting and capital arrangement for O Mon IV Thermal Power Plant Project
Tender/ Prequalification Notice ID
Contract execution period
43 months
Domestic/ International
International
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Financial consulting for the Project Consulting on capital mobilization plans for the Project; Implement capital arrangement contract; Complete disbursement procedures; Other contents serving the capital arrangement for the Project as agreed by the Parties.
Capital source details
Owner
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
By time and by output
Prequalification
No
Implementation location (After merge)
Ô Môn District, Cần Thơ
Implementation location (Before merge)
Can Tho city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for O Mon IV Thermal Power Plant Project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email