Bidder Selection Plan

Contractor selection plan for Phan Ngoc Hien Square construction investment project

  Watching  
Project Contractor selection plan Bid award
Find: 15:27 15/03/2024
Contractor Selection Plan ID
PL2400033229-00
Publishing time
15:26 15/03/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for Phan Ngoc Hien Square construction investment project
Project management forms
The investor directly manages the project
Using ODA capital?
Have
Funding source
ODA capital
Project number
PR2400009743-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
2 Years
Authority that issues the decision
Ủy Ban Nhân dân tỉnh Cà Mau
Approval date
15/03/2024
Approval ID
496/QĐ-UBND ngày 15/3/2024
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 13
1.Tender package No 01: Setting up the survey task for the preparation of TKBVTC
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Setting up the survey task of setting up the TKBVTC
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
2.Tender package No 02: Topographic survey and construction drawing design
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Category: + Ground leveling, Drainage system, Road system, Internal road yard, tree basin, Square nameplate, Lake, symbolic foundation, Green tree system, Rest huts (4 huts), Parking lot, public toilet area, technical house, + Central stage, artistic water spray system; + Water supply system; + Overall power supply system; + Lighting and communication systems.
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
3.Bidding package No. 03: Preparation of Bidding Documents, evaluation of Proposal for the package of consulting, surveying and preparing construction drawing design - estimates
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bids, evaluate bids for survey consulting packages and prepare construction drawing designs - estimates
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
4.Bidding package No. 04: Appraisal of request documents and results of evaluation of proposal documents for survey consulting and preparation of construction drawing designs - estimates
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of request documents and results of evaluation of proposal documents for survey consulting and preparation of construction drawing designs - estimates
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
5.Tender package No 05: Geological survey step to create construction drawing design
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Geological survey steps to create construction drawing design
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
6.Bidding package No. 06: Prepare an estimate outline to prepare documents for environmental licensing
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare an outline for preparing an environmental permit application
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
7.Bidding package No. 07: Prepare documents for environmental licensing
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare an application for an environmental permit
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
8.Tender package No 08: Verification of construction drawing design - estimates for items: Ground leveling, Drainage system, Road system, Internal road yard, tree basin, Square nameplate, Lake , symbolic foundation, Greenery system, Rest huts (4 huts), Parking lot, Public toilet area, technical house
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of construction drawing design - cost estimates for items: Ground leveling, Drainage system, Road system, Internal road yard, tree basin, Square nameplate, Lake, symbolic foundation, Green tree system, Rest huts (4 huts), Parking lot, Public restrooms, technical house
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
9.Tender package No 09: Verification of construction drawing design - cost estimates for items: Central stage, Artistic water spray system
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of construction drawing design - cost estimates for items: Central stage, Artistic water spray system
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
10.Bidding package No. 10: Verification of construction drawing design - cost estimate for item: Water supply system
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verify construction drawing design - estimate for item: Water supply system
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
11.Bidding package No. 11: Verification of construction drawing design - cost estimate for item: Overall power supply system
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verify construction drawing design - item estimate: Overall power supply system
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
12.Bidding package No. 12: Verification of construction drawing design - cost estimates for items: Lighting and communication systems
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of construction drawing design - cost estimates for items: Lighting and communication systems
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province
13.Tender package No 13: Supervision of survey work and construction drawing design steps
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise the survey work and prepare construction drawing designs
Capital source details
Provincial budget in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Cà Mau City, Cà Mau
Implementation location (Before merge)
Ca Mau province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for Phan Ngoc Hien Square construction investment project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for Phan Ngoc Hien Square construction investment project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 48

You did not use the site, Click here to remain logged. Timeout: 60 second