Bidder Selection Plan

Contractor selection plan for phase 2 of Barracks 602/BTM-HQ construction investment project

  Watching      
Find: 09:56 20/06/2024
Contractor Selection Plan ID
PL2400002353-01
Publishing time
09:55 20/06/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for phase 2 of Barracks 602/BTM-HQ construction investment project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400000737-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
Bộ Quốc phòng
Approval date
04/06/2024
Approval ID
2303/QĐ-BQP
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Total investment, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 14
1.Tender package TV-06
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Geological survey drilling (stage of preparing TKBVTC-DT documents)
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
2.Package TV-07a: Prepare design documents for architectural and technical infrastructure works (excluding work content in package TV-07)
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
3.Bidding package TV-08a
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of documents on TKBVTC-TDT for architectural works and technical infrastructure (not including work content in bidding package TV-08)
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
4.Tender package TV-09
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Static compression test of reinforced concrete piles
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
5.Bidding package TV-10a
Tender/ Prequalification Notice ID
Contract execution period
700 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction and installation of architectural works and technical infrastructure (not including work content in bidding package TV-10)
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
6.Package XL-02
Tender/ Prequalification Notice ID
Contract execution period
250 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of a 250-seat restaurant; Fleet Housing; Car garage; Motorbike garage
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
7.Bidding package XL-03
Tender/ Prequalification Notice ID
Contract execution period
320 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of general warehouse; Some auxiliary works and technical infrastructure of Area A (gates, guard posts; leveling; yards, internal roads; wastewater treatment)
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
8.Bidding package XL-04
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of working house No. 2; 300-seat restaurant; House on duty; Motorbike garage (02 houses); Repair workshop, technical maintenance, warehouse; Warehouse K36B; Some auxiliary works and technical infrastructure of Area B (gates, guard posts; leveling; yards, internal roads; wastewater treatment...)
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
9.Bidding package XL-05
Tender/ Prequalification Notice ID
Contract execution period
320 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and installation of outdoor electrical systems (including substations, RMU cabinets)
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
10.Bidding package XL-07
Tender/ Prequalification Notice ID
Contract execution period
250 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Anti-termite (Zone A, Zone B)
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
11.Package XL-08
Tender/ Prequalification Notice ID
Contract execution period
400 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of fire protection items in Area A and Area B (including fire pumps)
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
12.Bidding package XL-09
Tender/ Prequalification Notice ID
Contract execution period
400 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Moving and planting additional trees (Area A, Area B)
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
13.Tender package PTV-01
Tender/ Prequalification Notice ID
Contract execution period
750 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
Government budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city
14.Package MS-01
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Procurement and installation of tools and equipment (excluding fire pumps and wastewater treatment equipment)
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hải An District, Hải Phòng
Implementation location (Before merge)
Hai Phong city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for phase 2 of Barracks 602/BTM-HQ construction investment project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for phase 2 of Barracks 602/BTM-HQ construction investment project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 29

You did not use the site, Click here to remain logged. Timeout: 60 second