Bidder Selection Plan

Contractor selection plan for project implementation phase Project: Repair and embellish Trung Thuong Temple relic, Dai Hung commune, Ung Hoa district, city. Hanoi

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 20:42 25/12/2025
Contractor Selection Plan ID
PL2500366444-00
Publishing time
20:41 25/12/2025
Posting Status
Published
Contractor selection plan name
Contractor selection plan for project implementation phase Project: Repair and embellish Trung Thuong Temple relic, Dai Hung commune, Ung Hoa district, city. Hanoi
Bid Solicitor
Investment objective
-Renovate and embellish the Trung Thuong Temple relic to preserve the original ancestors, preserve long-term and promote the historical and cultural value of the relic. - Construction of the monument's infrastructure is synchronous, the overall site of the monument is repaired and embellished in accordance with the inherent space and landscape of the monument. Meet the spiritual, cultural and religious needs of the people. - Meet the visiting needs of local and foreign visitors Learn about the cultural history of Ung Hoa district in general and the Trung Temple relic
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500072469-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
UBND xã Ứng Hoà
Approval date
22/12/2025
Approval ID
2766/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 8
1.Prepare design of financial protection - total estimate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare construction drawings - estimates
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Verification of BVTC design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of construction drawing design and cost estimate
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Making Bidding Documents, evaluating bidding for construction construction
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Preparation of bidding documents, evaluation of construction bids
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Appraisal of bidding documents and LCNT results for construction
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents, appraisal of LCNT finalization for construction
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Construction
Tender/ Prequalification Notice ID
Contract execution period
365 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
365 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction and installation package
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
7.Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
730 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
By percentage
Prequalification
No
Implementation location (After merge)
8.Audit
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit
Capital source details
city budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter IV, 2027
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for project implementation phase Project: Repair and embellish Trung Thuong Temple relic, Dai Hung commune, Ung Hoa district, city. Hanoi". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for project implementation phase Project: Repair and embellish Trung Thuong Temple relic, Dai Hung commune, Ung Hoa district, city. Hanoi" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 1

You did not use the site, Click here to remain logged. Timeout: 60 second