Bidder Selection Plan

Contractor selection plan for project preparation phase component 1: Compensation, support, resettlement, site clearance under the investment project: Son La - Dien Bien - Tay Trang border gate section (phase 1)

  Watching  
Project Contractor selection plan Bid award
Find: 08:56 21/08/2026
Contractor Selection Plan ID
PL2600118648-01
Publishing time
08:55 21/08/2026
Posting Status
Published
Contractor selection plan name
Contractor selection plan for project preparation phase component 1: Compensation, support, resettlement, site clearance under the investment project: Son La - Dien Bien - Tay Trang border gate section (phase 1)
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Spending Category
Investment and Development Spending
Authority that issues the decision
Ban Quản lý dự án các công trình Giao thông tỉnh Điện Biên
Approval date
17/08/2026
Approval ID
1552/QĐ-BCTGT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 8
1.Set up survey tasks to build the Feasibility Study Report step
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out survey tasks to serve the preparation of the Feasibility Study Report
Capital source details
Local budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
2.Consulting on construction surveys for the Feasibility Study Report step
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction surveys to prepare feasibility study reports
Capital source details
Local budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
Fixed unit price
Implementation location
Prequalification
No
3.Consulting on survey supervision and construction of the Feasibility Study Report step
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction survey supervision to prepare feasibility study reports
Capital source details
Local budget capital
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
4.Consulting on planning the overall resettlement area and announcing the planning
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Implement the master plan of the resettlement area and announce the plan
Capital source details
Local budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
5.Consultancy on making feasibility study report
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Making feasibility research reports
Capital source details
Local budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
6.Consultancy on verification of Feasibility Study Report
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out the examination of feasibility research reports
Capital source details
Local budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
7.Consulting on making environmental impact assessment report
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Make environmental impact assessment reports
Capital source details
Local budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
8.Consultation on developing a plan for reforestation payments and preparing documentation for changing forest land use.
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Implement a plan for compensating for forest loss through reforestation, and prepare the necessary documentation to change the land use purpose.
Capital source details
Local budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for project preparation phase component 1: Compensation, support, resettlement, site clearance under the investment project: Son La - Dien Bien - Tay Trang border gate section (phase 1)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for project preparation phase component 1: Compensation, support, resettlement, site clearance under the investment project: Son La - Dien Bien - Tay Trang border gate section (phase 1)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 1

You did not use the site, Click here to remain logged. Timeout: 60 second