Bidder Selection Plan

Contractor selection plan for the project: Glass roof system and automatic sun-blocking curtains for the first floor lobby area - Agribank Hanoi branch headquarters

  Watching      
Find: 05:53 04/10/2024
Contractor Selection Plan ID
PL2400220483-00
Publishing time
05:50 04/10/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for the project: Glass roof system and automatic sun-blocking curtains for the first floor lobby area - Agribank Hanoi branch headquarters
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400032985-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Other project
Project implementation time
2024 Years
Authority that issues the decision
Ngân hàng Nông nghiệp và Phát triển Nông thôn Việt Nam - Chi nhánh Hà Nội
Approval date
20/09/2024
Approval ID
3411/QĐ-NHNo.HN-TH
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 6
1.Package 4: Consulting on contractor selection
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Build bidding documents and evaluate bidding documents
Capital source details
Agribank's asset repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hai Bà Trưng District, Hà Nội
Implementation location (Before merge)
Ha Noi city
2.Bidding package No. 5: Consulting on appraisal of bidding documents and contractor selection results
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Evaluate bidding documents and contractor selection results
Capital source details
Agribank's asset repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hai Bà Trưng District, Hà Nội
Implementation location (Before merge)
Ha Noi city
3.Package 6: Project management consulting
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Project management consultancy
Capital source details
Agribank's asset repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hai Bà Trưng District, Hà Nội
Implementation location (Before merge)
Ha Noi city
4.Package 7: Construction supervision consultancy and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
35 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultancy of construction supervision and equipment installation
Capital source details
Agribank's asset repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hai Bà Trưng District, Hà Nội
Implementation location (Before merge)
Ha Noi city
5.Tender package No 8: Construction
Tender/ Prequalification Notice ID
Contract execution period
35 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction
Capital source details
Agribank's asset repair capital
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hai Bà Trưng District, Hà Nội
Implementation location (Before merge)
Ha Noi city
6.Tender package No 9: Audit
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit
Capital source details
Agribank's asset repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hai Bà Trưng District, Hà Nội
Implementation location (Before merge)
Ha Noi city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for the project: Glass roof system and automatic sun-blocking curtains for the first floor lobby area - Agribank Hanoi branch headquarters". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for the project: Glass roof system and automatic sun-blocking curtains for the first floor lobby area - Agribank Hanoi branch headquarters" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 18

You did not use the site, Click here to remain logged. Timeout: 60 second