Bidder Selection Plan

Contractor selection plan for the project implementation phase: Public lighting infrastructure in Lien Phuong, Ha Hoi, Thu Phu, Van Tao communes and Thuong Tin town, Thuong Tin district, Hanoi city

  Watching      
Find: 13:11 23/09/2024
Contractor Selection Plan ID
PL2300143801-01
Publishing time
10:10 23/09/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for the project implementation phase: Public lighting infrastructure in Lien Phuong, Ha Hoi, Thu Phu, Van Tao communes and Thuong Tin town, Thuong Tin district, Hanoi city
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300038765-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
Ủy ban nhân dân huyện Thường Tín
Approval date
19/09/2024
Approval ID
Số 3757/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Total investment, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 10
1.Tender package No 01: Consulting on making construction design documents and deploying after basic design
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
2.Bidding package No. 02: Consultancy on preparation of Bid Documents, evaluation of Bid Tender package No 01
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
3.Package 03: Consultancy on appraisal of bidding documents, LCNT results of package 01
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
4.Package 04: Consultancy and verification of BVTC design - estimate
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
5.Package 05: The whole part of construction work and ensure traffic safety
Tender/ Prequalification Notice ID
Contract execution period
390 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
The entire construction part of the project and ensuring traffic safety
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
Thường Tín District, Hà Nội
Implementation location (Before merge)
Ha Noi city
6.Package 06: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
390 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision consultancy
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thường Tín District, Hà Nội
Implementation location (Before merge)
Ha Noi city
7.Bidding package No. 07: Consulting on setting up Bidding Documents, evaluating bids of packages No. 05, 06
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents, evaluate bidding documents for package No. 05, 06
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thường Tín District, Hà Nội
Implementation location (Before merge)
Ha Noi city
8.Tender package No 08: Bidding appraisal consultancy, LCNT results of package No. 05, 06
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents and LCNT results for package No. 05, 06
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
9.Package 09: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
390 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
10.Package 10: Electrical testing consultancy, grounding pile
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Electrical testing, grounding stakes
Capital source details
District budget and other legal sources of funds
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thường Tín District, Hà Nội
Implementation location (Before merge)
Ha Noi city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for the project implementation phase: Public lighting infrastructure in Lien Phuong, Ha Hoi, Thu Phu, Van Tao communes and Thuong Tin town, Thuong Tin district, Hanoi city". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for the project implementation phase: Public lighting infrastructure in Lien Phuong, Ha Hoi, Thu Phu, Van Tao communes and Thuong Tin town, Thuong Tin district, Hanoi city" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 40

You did not use the site, Click here to remain logged. Timeout: 60 second