Bidder Selection Plan

Contractor selection plan for Tinh Vo Club Renovation project (Area C)

  Watching      
Find: 15:17 18/12/2024
Contractor Selection Plan ID
PL2400316915-01
Publishing time
15:16 18/12/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan for Tinh Vo Club Renovation project (Area C)
Investment objective
- In order to limit the deterioration of the project, ensure safety in use as well as ensure fire safety, and at the same time arrange the Center's activities to meet the medium's needs. is a place to practice and compete in sports. - Implement Resolution 23/2017/NQ-HDND of the People's Council of Ho Chi Minh City regulating the handling of establishments that do not meet fire prevention and fighting requirements in Ho Chi Minh City. was put into use before the date of the Law on Fire Prevention and Control
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400077456-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
720 Date
Authority that issues the decision
Ủy Ban nhân dân Quận 5
Approval date
13/12/2024
Approval ID
4258/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 6
1.Consultancy on preparation of bidding documents, evaluation of bids for construction bidding packages and equipment supply and installation
Tender/ Prequalification Notice ID
Contract execution period
50 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents, evaluate construction bids and supply and install equipment
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Implementation location (After merge)
Prequalification
No
2.Consulting on appraisal of bidding documents and appraisal of results of selection of construction contractors and equipment supply and installation
Tender/ Prequalification Notice ID
Contract execution period
50 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out appraisal of bidding documents, bid documents and results of contractor selection for construction and equipment supply and installation packages.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Implementation location (After merge)
Prequalification
No
3.construction and equipment supply and installation
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction and supply and install equipment
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Implementation location (After merge)
Prequalification
No
4.Construction supervision consultancy and equipment supply and installation
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise construction bidding packages and supply and install equipment
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Implementation location (After merge)
Prequalification
No
5.Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out project insurance work
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Implementation location (After merge)
Prequalification
No
6.Audit consulting
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Independent audit of finalization of completed projects
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for Tinh Vo Club Renovation project (Area C)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for Tinh Vo Club Renovation project (Area C)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 15

You did not use the site, Click here to remain logged. Timeout: 60 second