Bidder Selection Plan

Contractor selection plan (investment preparation phase) for the project Construction of a cultural house combined with a sports field in Phu Hoa hamlet, Phi Thong commune

  Watching  
Project Contractor selection plan Bid award
Find: 10:05 18/06/2024
Contractor Selection Plan ID
PL2400069810-01
Publishing time
10:05 18/06/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan (investment preparation phase) for the project Construction of a cultural house combined with a sports field in Phu Hoa hamlet, Phi Thong commune
Investment objective
In order to meet the infrastructure and living needs of cultural and artistic exchanges as well as organize entertainment activities for people in the area to meet the national target program of building new rural areas of Vietnam. Phi Thong commune
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400019634-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Authority that issues the decision
ỦY BAN NHÂN DÂN THÀNH PHỐ RẠCH GIÁ
Approval date
15/11/2023
Approval ID
1103/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Lowest bid price, Highest bid price, Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 3
1.Consulting on Preparation of Finance and Technical Report
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget (revenue for land use)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
Rạch Giá City, Kiên Giang
2.Consultancy and verification of construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget (revenue for land use)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
Rạch Giá City, Kiên Giang
3.Consultancy on appraisal of material prices
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget (revenue for land use)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
Rạch Giá City, Kiên Giang

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (investment preparation phase) for the project Construction of a cultural house combined with a sports field in Phu Hoa hamlet, Phi Thong commune". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (investment preparation phase) for the project Construction of a cultural house combined with a sports field in Phu Hoa hamlet, Phi Thong commune" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 2

You did not use the site, Click here to remain logged. Timeout: 60 second