Contractor Selection Plan ID
PL2300000695-07
Publishing time
14:21 31/05/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan (phase 1) under the major repair plan in 2023
Name of project
Major repair plan in 2023
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
Other
Authority that issues the decision
Công ty Truyền tải điện 2
Approval date
31/05/2022
Approval ID
660/QĐ-PTC2
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Bidding package number, total investment, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date (View changes)

- Change: Publication date (View changes)

- Change: Bidding package number, total investment, Highest bid price, Publication date, Bidding package information (View changes)

- Change: Bidding package number, total investment, Lowest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 45
1.Tender package No 30: Repairing equipment support pillars, transformer foundations, gate pillars of Dong Ha 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
2.Tender package No 11: Repairing shift rest houses, working houses, MBA fire prevention walls and 500kV Thanh My substation fences
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
3.Package 13: Supplying VTTB (including installation and maintenance) to repair fire protection systems of 500kV Doc Soi substations, 220kV Dung Quat substations
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
4.Tender package No 31: Repairing protective fence of Phong Dien 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
5.Package 34: Repair of control house, shift house and pump house of 220kV Tam Ky substation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
6.Package 37: Improving the phase–soil distance to prevent breakdowns at high loads at column range 278 - 279, 309 - 310 500kV line 578 Pleiku - 571 Doc Soi under the management of Quang Ngai Power Center
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
7.Package 38: Repairing foundation embankment at 500kV lines, 574 Vung Ang- 575 Da Nang, 574 Da Nang- 574 Ha Tinh under the management of Thua Thien Hue Power Center
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
8.Tender package No 1: Supplying 500kV Doc Soi 500kV OLTC MBA AT4 TBA actuators
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
9.Tender package No 7: Supply of optical transmission equipment (including installation, declaration and configuration services) 272 substation 220kV Quang Ngai
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
July 2023
Type of contract
All in One
Prequalification
No
Location
10.Package 9: Supply (including installation) outdoor lighting for 500kV Da Nang substation, 500kV Doc Soi substation
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
11.Package 21: Repairing the grounding system to ensure effective lightning discharge at 500kV and 220kV power lines under the management of Quang Ngai Power Center
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
12.Package 3: Supplying VTTB for repair of Isolators of 500kV and 220kV substations under the management of PTC2
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
13.Package 16: Providing VTTB (including construction and installation) to serve the installation of towing ropes, installation of support chains, repair of damaged conductors at 500kV and 220kV transmission positions and anchorages under the management of PTC2.
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
14.Package 17: Repairing the grounding system to ensure effective lightning discharge at 500kV and 220kV lines under the management of Quang Binh Power Center
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
15.Tender package No 24: Supplying lightning arrester for 220kV Dong Hoi TBA valve
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
16.Tender package No 28: Repairing contact resistance meter CA 10 TBA 220kV Quang Ngai
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
17.Tender package No 29: Repairing FLIR E30 TBA 220kV Quang Ngai thermal imaging camera
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
18.Tender package No 32: Repairing control house, shift house of Thanh My 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
19.Tender package No 12: Repairing the control house, flying housing, motel at 220kV Quang Ngai substation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
20.Package 23: Overhaul Toyota Camry with registration number 43K - 6739 belonging to the company's office transport vehicle
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
21.Tender package No 35: Repairing protective fence of 500kV Doc Soi substation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
22.Tender package No 25: Repairing the second circuit of 220kV, 110kV Thanh My substation 220kV
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
23.Tender package No 46: Repairing Kia cars with control plate 43C - 06402 belonging to the means of transport of Quang Ngai Central Power Corporation
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
24.Tender package No 40: Supply of nameplates of lines for repairing 220kV telephones 273, 274 Dong Hoi - 273 BT1; 272 BT1 - 274 Dong Ha belongs to Quang Binh Central Region
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
25.Package 41: Repairing the ground ground of Dong Hoi TTC Team
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
26.Package 42: Overhaul UAZ cars with registration number 43B-019.07 belonging to Quang Binh vehicles
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
27.Tender package No 43: Overhaul Ford Ranger with registration number 43H-1373, 43H-0183 belonging to Quang Tri transmission vehicle
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
28.Package 44: Overhaul Ford Ranger car registration number 43H-4907 belonging to Thua Thien Hue TTC transport vehicle
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
29.Tender package No 45: Overhaul Ford Ranger car registration number 43H - 5249, 43H - 5413 belonging to the means of transport of Quang Nam TTC
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
30.Package 26: Supplying VTTB (including installation and installation) of ENGINEERING TBA 220kV Thanh My computer
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
31.Package 33: Repair of control house, shift guesthouse, flying housing, hazardous waste house, pump house, security house, 220kV Song Tranh 2 substation fire tank
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
32.Tender package No 36: Improving the phase-earth distance to prevent breakdowns when high loads are at the poles of 220kV line 271 Hue-272 Song Bo Power Plant, 275, 276 Hoa Khanh-273, 272 Hue under the management of Thua Thien Hue Power Center.
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
33.Package 2: Supply of internal protection relays for transformers of 500kV Doc Soi substation, Tam Ky 220kV substation and Dung Quat 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
34.Package 4: Supplying VTTB for repair of 22kV Hue 220kV substation, Quang Ngai 220kV substation
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
35.Package 5: Supply (including installation and installation) of transmission equipment for 273 substation 220kV Hoa Khanh, 275 substation 220kV Thanh My
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
36.Package 6: Supplying VTTB for protection relay repair (including configuration installation) at 220kV Quang Ngai substation
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
37.Package 10: Repairing sidewalks and internal roadbeds of 220kV Dong Hoi substation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
38.Package 14: Construction of rusty rods and bolts (including paint supply) for 500kV and 220kV transmission lines under the management of PTC2
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
39.Package 15: Supply of insulation and accessories (including installation) for the repair of 500kV, 220kV lines managed by PTC2
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
40.Package 20: Repairing the grounding system to ensure effective lightning discharge at 500kV and 220kV lines under the management of Quang Nam Power Center
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
41.Tender package No 22: Repairing the outdoor yard and repainting the fence of Quang Tri Center for Production and Production House, Vinh Linh Center for Cultural Management House
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
42.Package 19: Repairing the grounding system to ensure effective lightning discharge at 500kV and 220kV lines under the management of Da Nang Power Corporation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
43.Package 8: Supplying VTTB (including installation and configuration) for the repair of Kon Tum transmission equipment of the PTC2 video conferencing system
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
44.Package 18: Repairing the grounding system to ensure effective lightning discharge at 500kV and 220kV power lines under the management of Quang Tri Power Center
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
45.Tender package No 27: Repairing 500kV substation air conditioning system in Da Nang
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Major repair in 2023
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (phase 1) under the major repair plan in 2023". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (phase 1) under the major repair plan in 2023" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 24

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8468 Projects are waiting for contractors
  • 533 Tender notices posted in the last 24 hours
  • 551 Contractor selection plan posted in the last 24 hours
  • 24924 Tender notices posted in the past month
  • 38740 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second