Bidder Selection Plan

Contractor selection plan (phase 2) Con Quy port construction project, Quan Lan commune, Van Don district

  Watching  
Project Contractor selection plan Bid award
Find: 14:28 13/01/2026
Contractor Selection Plan ID
PL2600008191-00
Publishing time
14:27 13/01/2026
Posting Status
Published
Contractor selection plan name
Contractor selection plan (phase 2) Con Quy port construction project, Quan Lan commune, Van Don district
Investment objective
According to the project approval decision
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500050833-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng đặc khu Vân Đồn
Approval date
06/01/2026
Approval ID
01/QĐ-DA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 2
1.Package No. 06: Construction of mines and mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
13 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of clearing mines and explosives
Capital source details
According to Decision No. 3989/QD-UBND dated December 26, 2025 of the People's Committee of Van Don Special Zone
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Package No. 07: Consulting supervision of construction and construction of mines and mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
13 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervising the clearance of mines and explosives
Capital source details
According to Decision No. 3989/QD-UBND dated December 26, 2025 of the People's Committee of Van Don Special Zone
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (phase 2) Con Quy port construction project, Quan Lan commune, Van Don district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (phase 2) Con Quy port construction project, Quan Lan commune, Van Don district" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second