Bidder Selection Plan

Contractor selection plan (phase 3) - Major repair plan in 2026

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 10:07 30/10/2025
Contractor Selection Plan ID
PL2500273385-00
Publishing time
10:05 30/10/2025
Posting Status
Published
Contractor selection plan name
Contractor selection plan (phase 3) - Major repair plan in 2026
Name of project
Big repair plan 2026
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
Other
Authority that issues the decision
Công ty Truyền tải điện 2
Approval date
28/10/2025
Approval ID
2749/QĐ-PTC2
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 2
1.Package 29.VT.SCL2026: Supply VTTB to repair vertical capacitors for 500kV Da Nang and 500kV Thanh My substations
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Equipped with Platform Fiber Optic optical interface (PFOI): 03 sets Equipped with high pressure capacitors: 06 bottles Additional supplies included
Capital source details
Large repair in 2026
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Package 30.VT.SCL2026: Supply VTTB to repair disconnectors, current transformers, voltage transformers for 220kV-500kV substations managed by PTC2
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Repair 42 sets of DCL blades 171-1, 171-2, 171-7, 172-2, 173-1, 173-2, 173-7, 174-1, 174-2, 174-7, 132-1, 132-2, 132-3, 112-2 Dong Ha 220kV substation - Repair 02 sets of DCL blades KT502-0, KT591-0 500kV reactor compartment Thanh My 500kV substation - Repair 09 sets of isolation blades 232-1, 175-2, 177-2 Da Nang 500kV substation - Equipped with 07 TI sets, 15 TU sets and accompanying accessories.
Capital source details
Large repair in 2026
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (phase 3) - Major repair plan in 2026". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (phase 3) - Major repair plan in 2026" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 4

You did not use the site, Click here to remain logged. Timeout: 60 second