Bidder Selection Plan

Contractor selection plan (phase 3) Project "Building infrastructure to adapt to climate change for ethnic minorities (CRIEM) - Component project of Quang Tri province"

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 21:12 21/12/2025
Contractor Selection Plan ID
PL2500356782-00
Publishing time
21:11 21/12/2025
Posting Status
Published
Contractor selection plan name
Contractor selection plan (phase 3) Project "Building infrastructure to adapt to climate change for ethnic minorities (CRIEM) - Component project of Quang Tri province"
Investment objective
- Overall goal of the Project: Improve opportunities for livelihood development, reduce poverty and inequality for ethnic minorities through developing integrated infrastructure investment to adapt to climate change. - Specific objective: Invest in upgrading transportation infrastructure and improving production infrastructure to support economic development for ethnic minorities.
Project management forms
The investor directly manages the project
Using ODA capital?
Have
Funding source
ODA capital
Project number
PR2400015517-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
6 Years
Authority that issues the decision
BAN QUẢN LÝ DỰ ÁN ĐẦU TƯ XÂY DỰNG TỈNH QUẢNG TRỊ
Approval date
16/12/2025
Approval ID
761/QĐ-BQLDA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 10
1.Upgrading Khe Sanh - Sa Tram road, Huong Hoa district
Tender/ Prequalification Notice ID
Contract execution period
22 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
ADB
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of Khe Sanh - Sa Tram road, Huong Hoa district
Capital source details
ADB funding and counterpart capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
2.Upgrading the inter-village road Cha Ly - Cu Bai, Huong Lap commune, Huong Hoa district
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
ADB
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of the road inter-village Cha Ly - Cu Bai, Huong Lap commune, Huong Hoa district
Capital source details
ADB funding and counterpart capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
3.Upgrading the inter-commune road Huc - Ba Floor, Huong Hoa district
Tender/ Prequalification Notice ID
Contract execution period
22 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
ADB
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of inter-commune road Huc - Ba Floor, Huong Hoa district
Capital source details
ADB funding and counterpart capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
4.Upgrading the central road of A Doi commune, Huong Hoa district
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
ADB
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of central road in A Doi commune, Huong Hoa district
Capital source details
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
5.Upgrading the road from Dakrong district center to Ba Long commune, Huong Hoa district
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
ADB
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of road from Dakrong district center to Ba Long commune, Huong Hoa district
Capital source details
ADB funding and counterpart capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
6.CRIEM-TV42: Consulting on preparing bidding documents for package QT-CW1 "Upgrading Khe Sanh - Sa Tram road, Huong Hoa district"
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents for construction packages
Capital source details
Counterpart fund
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
7.CRIEM-TV43: Consulting on preparing bidding documents for package QT-CW2 "Upgrading the inter-village road Cha Ly - Cu Bai, Huong Lap commune, Huong Hoa district"
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents for construction packages
Capital source details
Counterpart fund
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
8.CRIEM-TV44: Consulting on preparing bidding documents for package QT-CW3 "Upgrading the Huc - Ba Floor inter-commune road, Huong Hoa district"
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents for construction packages
Capital source details
Counterpart fund
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
9.CRIEM-TV45: Consulting on preparing bidding documents for package QT-CW4 "Upgrading the central road of A Doi commune, Huong Hoa district"
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents for construction packages
Capital source details
Counterpart fund
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
10.CRIEM-TV46: Consulting on preparing bidding documents for package QT-CW5 "Upgrading road from Dakrong district center to Ba Long commune, Huong Hoa district"
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents for construction packages
Capital source details
Counterpart fund
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (phase 3) Project "Building infrastructure to adapt to climate change for ethnic minorities (CRIEM) - Component project of Quang Tri province"". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (phase 3) Project "Building infrastructure to adapt to climate change for ethnic minorities (CRIEM) - Component project of Quang Tri province"" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second