Bidder Selection Plan

Contractor selection plan Project: Completing and preventing overloading of the power grid in Nghia Hanh and Minh Long districts in 2024

  Watching      
Find: 16:39 11/10/2023
Contractor Selection Plan ID
PL2300188798-00
Publishing time
16:38 11/10/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan Project: Completing and preventing overloading of the power grid in Nghia Hanh and Minh Long districts in 2024
Investment objective
Ensuring power quality, reducing losses, developing the power grid and improving power supply reliability; Ensuring electrical safety among people and urban aesthetics
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300049861-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Location
Quang Ngai province
Authority that issues the decision
Công ty Điện lực Quảng Ngãi
Approval date
05/10/2023
Approval ID
7964/QĐ-QNPC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Tender package No 02/XL: Testing VTTB for the whole project
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Financial planning and credit and commercial loans construction investment plan in 2024
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
Is different
Prequalification
No
Location
2.Tender package No 05/TV: Acceptance, energizing and handing over the work
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Financial planning and credit and commercial loans construction investment plan in 2024
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
Is different
Prequalification
No
Location
3.Tender package No 03/XL: Connecting SCADA
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Financial planning and credit and commercial loans construction investment plan in 2024
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
Is different
Prequalification
No
Location
4.Tender package No 01/XL: Supply of materials (except for A grade materials) and construction and installation of works
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Financial planning and credit and commercial loans construction investment plan in 2024
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan Project: Completing and preventing overloading of the power grid in Nghia Hanh and Minh Long districts in 2024". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan Project: Completing and preventing overloading of the power grid in Nghia Hanh and Minh Long districts in 2024" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 5

You did not use the site, Click here to remain logged. Timeout: 60 second