Contractor selection plan Project: Equipping a relay system that complies with distribution power system regulations at 110kV transformer stations An Long, Tran Quoc Toan, An Hoa, Thanh Hung, NhaMan and Song Hau according to Project 100
Contractor selection plan Project: Equipping a relay system that complies with distribution power system regulations at 110kV transformer stations An Long, Tran Quoc Toan, An Hoa, Thanh Hung, NhaMan and Song Hau according to Project 100
Equipped with relay systems that comply with distribution power system regulations at 110kV substations of An Long, Tran Quoc Toan, An Hoa, Thanh Hung, NhaMan and Song Hau according to Project 100
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
96 - QD 14.01.2025-PD KHLCNT du an (Role theo de an 100).pdf
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements
- Change:Publication date, Bidding package information (View changes)
1.Package 10: Installation, testing, equipment calibration and configuration, checking project SCADA signals Equipping a relay system that complies with distribution power system regulations at 110kV transformer stations An Long, Tran Quoc Toan, An Hoa, Thanh Hung, Nha Man and Song Hau according to Project 100
2.Contract package: Consulting on construction supervision and installation of construction equipment Equipping relay systems in compliance with distribution power system regulations at 110kV transformer stations An Long, Tran Quoc Toan, An Hoa, Thanh Hung, Nha Man and Song Hau according to Project 100
3.Package 10.1: Construction and installation of construction equipment Equipping a relay system that complies with distribution power system regulations at 110kV transformer stations An Long, Tran Quoc Toan, An Hoa, Thanh Hung, Nha Man and Song Hau according to Project 100 (including calculation of protective relay adjustment parameters)
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan Project: Equipping a relay system that complies with distribution power system regulations at 110kV transformer stations An Long, Tran Quoc Toan, An Hoa, Thanh Hung, NhaMan and Song Hau according to Project 100". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan Project: Equipping a relay system that complies with distribution power system regulations at 110kV transformer stations An Long, Tran Quoc Toan, An Hoa, Thanh Hung, NhaMan and Song Hau according to Project 100" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.