Bidder Selection Plan

contractor selection plan Project: Installing the second transformer at 110kV Binh Loi substation

  Watching      
Find: 14:35 25/01/2021
Contractor selection plan ID
20210146714-00
Publication date
14:32 25/01/2021
Publication status
Actual notification
Contractor selection plan name
contractor selection plan Project: Installing the second transformer at 110kV Binh Loi substation
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210146702-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval date
25/01/2021
Approval ID
432/QĐ-EVNHCMC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

List of Bid:
Number of packages: 4
1.Package 01: Construction, supply and installation of VTTB, SCADA calibration testing and insurance purchase
Tender/ Prequalification Notice ID
Contract Period
105 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Construction investment capital of EVNHCMC
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
Contract Type
All in one
Prequalification
No
2.Tender package No 2: Construction supervision consultancy and equipment installation for the whole project
Tender/ Prequalification Notice ID
Contract Period
105 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Construction investment capital of EVNHCMC
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
Contract Type
All in one
Prequalification
No
3.Tender package No 3: Audit of works
Tender/ Prequalification Notice ID
Contract Period
165 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Construction investment capital of EVNHCMC
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
Contract Type
All in one
Prequalification
No
4.Tender package No 4: Calibration Experiment
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Construction investment capital of EVNHCMC
Contractor Selection Type
Self-implementation, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2021
Contract Type
All in one
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "contractor selection plan Project: Installing the second transformer at 110kV Binh Loi substation". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "contractor selection plan Project: Installing the second transformer at 110kV Binh Loi substation" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 96

You did not use the site, Click here to remain logged. Timeout: 60 second